ORS 543A.040
Process determination


(1)

Within 60 days after the close of the period allowed for public comment under ORS 543A.035 (Reauthorization application and public comment), the Hydroelectric Application Review Team shall determine whether the reauthorization application for the water right contains sufficient information to determine whether reauthorization of the state project will comply with ORS 543A.025 (Minimum standards for decision on reauthorization of water right).

(2)

If the team decides that sufficient information is available to determine whether reauthorization of the water right for the state project will comply with ORS 543A.025 (Minimum standards for decision on reauthorization of water right), the team shall proceed with expedited processing of the reauthorization application. The team shall review the application and any public comments received on the application and prepare a draft proposed final order, including findings of fact and conclusions of law, for the water right. Upon completion of the draft proposed final order, the team shall give public notice of the draft proposed final order in the weekly notice published by the Water Resources Department. The notice shall include a request for comments on the draft proposed final order.

(3)

Within 60 days after the public notice under subsection (2) of this section, any person interested in the draft proposed final order shall submit written comments to the team. A person who submits written comments under this subsection shall identify the provision of the draft proposed final order in question and specify why the person objects to or supports the provision. The team shall review the comments received and may revise the draft proposed final order. Unless the department receives a request under subsection (4) of this section, the team shall submit a proposed final order to the department within 30 days after the close of the period for public comment on the draft proposed final order.

(4)

If the draft proposed final order prepared by the team under subsection (2) of this section proposes to deny the application for reauthorization of the water right, the applicant may request the department to process the application in accordance with ORS 543A.045 (Public scoping meeting) to 543A.055 (Hydroelectric Application Review Team review of application). The applicant shall submit a request under this subsection within the 60-day period allowed for public comment on the draft proposed final order.

(5)

Unless the department receives a request under subsection (4) of this section, the department shall issue the proposed final order in accordance with the provisions of ORS 543A.120 (Proposed final order) to 543A.300 (Decommissioning).

(6)

If the team determines that additional information is necessary to determine whether reauthorization of the state project will comply with ORS 543A.025 (Minimum standards for decision on reauthorization of water right), the applicant shall comply with the process established in ORS 543A.045 (Public scoping meeting) to 543A.055 (Hydroelectric Application Review Team review of application) and 543A.120 (Proposed final order) to 543A.300 (Decommissioning). [1997 c.449 §8]

Source: Section 543A.040 — Process determination, https://www.­oregonlegislature.­gov/bills_laws/ors/ors543A.­html.

543A.005
Definitions
543A.010
Findings
543A.015
Purpose
543A.020
Policy
543A.025
Minimum standards for decision on reauthorization of water right
543A.030
Notice of intent
543A.035
Reauthorization application and public comment
543A.040
Process determination
543A.045
Public scoping meeting
543A.050
Application report
543A.055
Hydroelectric Application Review Team review of application
543A.060
Coordination of state and federal reauthorization processes
543A.065
Changes to expiration date of water right for existing project
543A.071
Water Resources Department notification to holder of hydroelectric license or water right for hydroelectric purposes
543A.075
Notice of intent to apply for reauthorization of right to use water for hydroelectric purposes
543A.080
Submission of preliminary application information
543A.085
Public scoping meeting
543A.090
Mid-study status report
543A.095
Draft application
543A.100
Final application for water right
543A.105
Hydroelectric Application Review Team review of final application
543A.110
Water quality certification
543A.115
Final unified state position
543A.120
Proposed final order
543A.125
Approval or rejection of application for reauthorization
543A.130
Contested case hearing
543A.135
Exceptions to final order
543A.140
Terms, limitations and conditions of water right
543A.145
Water right certificate
543A.150
Modification of time limits
543A.300
Decommissioning
543A.305
Conversion of hydroelectric water right to in-stream water right
543A.400
Duties of Hydroelectric Application Review Team
543A.405
Application fees
543A.410
Fee schedule
543A.800
Effect of hydroelectric reauthorization process on existing rights
543A.805
Reference to licensee or license
543A.810
Effect of amendment or repeal of law
Green check means up to date. Up to date