Project ineligible activities include, but are not limited to:

(1)

The demolition and rebuild of an existing critical public building.

(2)

Rehabilitation to a building located in the Tsunami Inundation Zone as defined in OAR 104-050-0010 (Definitions).

(3)

Rehabilitation of a building located in the flood zone, with no previous mitigation activities completed.

(4)

Partial rehabilitation of a building that does not holistically address all known seismic deficiencies, as defined in OAR 104-050-0010 (Definitions).