Project ineligible activities include, but are not limited to:

(1)

The demolition and rebuild of an existing critical public building.

(2)

Rehabilitation to a building located in the Tsunami Inundation Zone as defined in OAR 123-051-0200(18).

(3)

Rehabilitation of a building located in the 100 year flood zone.

(4)

Partial rehabilitation of a building that does not holistically address all known seismic deficiencies, as defined in OAR 123-051-0200(11).

(5)

Reimbursement for already budgeted staff and routine or ongoing expenses of the recipient.