OAR 141-093-0310
Certain Ocean Renewable Energy Facilities - GP- Specific Conditions


(1) All requirements, procedures and conditions set forth in OAR 141-093-135 (General Conditions) apply to this General Permit, except as follows:
(a) General Condition (5) ODFW Fish Passage Requirement;
(b) General Condition (8) Pre-Construction Resource Area Fencing or Flagging;
(c) General Condition (9) Erosion Control Methods; and
(d) General Condition (11) Raising or Redirecting Water
(2) Notwithstanding the provisions of ORS 274.879 (Financial assurance)(8), the authorization holder must complete the removal of all equipment related to the ocean renewable energy facility within the term of the authorization, not to exceed five years, unless an individual removal-fill permit, pursuant to 141-085 has been issued for extended or expanded ocean renewable energy facility placement.
(3) Anchors, cables or any other equipment that lies at least one (1) meter beneath the ocean floor may be decommissioned in-place if:
(a) There is a recommendation from the JART to allow specified equipment to be decommissioned in-place; and,
(b) The authorization expressly allows specified equipment to be decommissioned in-place.
(3) Authorized facilities must contain fish screens as required by ODFW on any water intake or discharge devices associated with the ocean renewable energy facility.
(4) Any cables, pipes or other conduit extending to the ocean shore must be placed consistent with Part Four of the Territorial Sea Plan.
(5) Required notifications. The authorization holder must submit to the Department:
(a) For any approved decommissioning of equipment in-place, a letter verifying that the equipment is buried at least one (1) meter beneath the ocean floor. The letter must include a description of methods used to verify the burial depth of the equipment. This verification letter is due to the Department no later than 90 days prior to the initiation of facility decommissioning.
(b) A letter verifying the removal of all ocean renewable energy facility components (excluding any equipment authorized to be decommissioned in-place. This verification letter is due to the Department within 30 days of completing the removal.
(c) Notification of any observed sinking or disconnection of floating components, substantive movement of anchors from the point of placement, entanglement of fishing gear, any release of fluids or any exposure of any buried components. Notification is required within 24 hours of observance and must include a corrective action plan.

Source: Rule 141-093-0310 — Certain Ocean Renewable Energy Facilities - GP- Specific Conditions, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-093-0310.

141‑093‑0100
General
141‑093‑0103
Agency Process and Standards for Establishing General Permits
141‑093‑0104
Project Applicability
141‑093‑0105
Application Requirements and Completeness Review for Authorizing Projects under a General Permit
141‑093‑0107
Completeness and Eligibility Review for Authorizing Projects under a GP
141‑093‑0110
Public Review Process for Authorizing Projects under a GP
141‑093‑0115
Department Determinations and Considerations in Evaluating Applications to Authorize Projects under a GP
141‑093‑0120
Expiration and Annual Billing
141‑093‑0125
Enforcement
141‑093‑0130
Appeal Process for Authorizations Issued under General Permits
141‑093‑0135
General Conditions
141‑093‑0140
Transportation-Related Structures - Purpose
141‑093‑0141
Transportation-Related Structures - Eligibility Requirements
141‑093‑0145
Transportation-Related Structures - GP-Specific Application Requirements for Authorizing Projects
141‑093‑0150
Transportation-Related Structures - Authorized Activities
141‑093‑0151
Transportation-Related Structures - GP-Specific Conditions
141‑093‑0155
Minor Removal-Fill Impacts - Purpose
141‑093‑0160
Minor Removal-Fill Impacts - Eligibility Requirements
141‑093‑0165
Minor Removal-Fill Impacts - Compensatory Wetland Mitigation
141‑093‑0170
Minor Removal-Fill Impacts - Authorized Activities
141‑093‑0175
Minor Removal-Fill Impacts - GP-Specific Conditions
141‑093‑0180
Jackson County Vernal Pools - Purpose
141‑093‑0185
Jackson County Vernal Pools - Expiration
141‑093‑0187
Jackson County Vernal Pools - Review Process for Authorizing Projects
141‑093‑0190
Jackson County Vernal Pools - Definitions
141‑093‑0195
Jackson County Vernal Pools - Eligibility Requirements
141‑093‑0200
Jackson County Vernal Pools - Mitigation
141‑093‑0205
Jackson County Vernal Pools - Specific Application Requirements
141‑093‑0215
Jackson County Vernal Pools - Specific Conditions
141‑093‑0220
Maintenance Drainage - Purpose
141‑093‑0225
Maintenance Drainage - Eligibility Requirements
141‑093‑0230
Maintenance Drainage - Specific Application Requirements
141‑093‑0235
Maintenance Drainage - Authorized Activities
141‑093‑0240
Maintenance Drainage - Specific Conditions
141‑093‑0245
Maintenance Drainage - Fees
141‑093‑0250
Maintenance Dredging - Purpose
141‑093‑0255
Maintenance Dredging - Definitions
141‑093‑0260
Maintenance Dredging - Eligibility Requirements
141‑093‑0265
Maintenance Dredging - Specific Application Requirements
141‑093‑0270
Maintenance Dredging - Authorized Activities
141‑093‑0275
Maintenance Dredging - Specific Conditions
141‑093‑0280
Maintenance Dredging - Term and Reporting
141‑093‑0285
Certain Ocean Renewable Energy Facilities - GP-Purpose
141‑093‑0290
Certain Ocean Renewable Energy Facilities - GP-Definitions
141‑093‑0295
Certain Ocean Renewable Energy Facilities - GP-Eligibility Requirements
141‑093‑0300
Certain Ocean Renewable Energy Facilities - GP-Specific Application Requirements
141‑093‑0305
Certain Ocean Renewable Energy Facilities - GP-Authorized Activities
141‑093‑0310
Certain Ocean Renewable Energy Facilities - GP- Specific Conditions
Last Updated

Jun. 8, 2021

Rule 141-093-0310’s source at or​.us