OAR 330-135-0010
Purpose


The purpose of these rules is to establish procedures to administer ORS 279C.527 (Inclusion of amount for green energy technology or woody biomass energy technology in public improvement contract) through 279C.528 (State Department of Energy requirements and specifications) and Oregon Laws 2019 chapter 160 (HB 2496), which require a contracting agency to include an appropriate green energy technology, or if green energy technology is not appropriate an eligible alternative to green energy technology in the construction, reconstruction, or major renovation of a public building by spending an amount equal to at least 1.5 percent of the total contract price associated with that building.
Last Updated

Jun. 8, 2021