OAR 330-230-0020
Purpose of Inspection or Review


(1)

The department may require project inspection or project review at any time from the date of initial application through the end of a project’s period of operation.

(2)

Inspections or reviews may be conducted by the department to verify:

(a)

The amount certified for a credit,

(b)

Completion of a project,

(c)

A project is operational,

(d)

Ownership of a project,

(e)

Compliance with the preliminary certificate or application for preliminary certification and any amendments,

(f)

Compliance with a performance agreement, or

(g)

Compliance with ORS Chapter 469B (Energy Incentives) and any applicable rules or standards adopted by the director.

(3)

The applicant or its designated representative must be present during the inspection or review.

Source: Rule 330-230-0020 — Purpose of Inspection or Review, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=330-230-0020.