OAR 330-240-0030
Project Eligibility


(1) To be eligible for a rebate for the sale, construction, or installation of a solar electric system or a paired solar and storage system, the system must meet the following requirements:
(a) The solar electric system or paired solar and storage system must be installed by an eligible contractor. The contractor may use subcontractors in the construction or installation of a solar electric system or paired solar and storage system; however, all firms and individuals working on the construction or installation of a solar electric system or paired solar and storage system, whether working on behalf of the contractor or a subcontractor, must hold any license, bond, insurance or permit required for the work performed.
(b) In the case of a paired solar and storage system, the solar electric system and energy storage system must be purchased together from the same eligible contractor.
(c) In the case of a paired solar and storage system, the solar electric system and associated energy storage must be constructed and installed together by the same eligible contractor or a subcontractor working for the eligible contractor, as provided in subparagraph (a), such that the energy storage system is capable of providing storage capacity for electrical energy produced by the solar electric system.
(d) In the case of a paired solar and storage system, the system must include a minimum of one kilowatt DC of solar electric nameplate capacity for every five kilowatt-hours of battery storage.
(e) The purchase contract for a solar electric system or paired solar and storage system must be signed on or after January 1, 2020.
(f) A contractor must submit a reservation application before starting construction or installation of a solar electric system or paired solar and storage system in order to be eligible for a rebate.
(g) The solar electric system or paired solar and storage system must be installed on real property in Oregon.
(h) The solar electric system or paired solar and storage system must benefit a residential customer or a low-income service provider as defined in these rules.
(i) The solar electric system or paired solar and storage system must consist of new equipment.
(j) In the case of a solar electric system, the system must contain all components necessary to convert and deliver solar energy into electrical energy for use in a dwelling or commercial application.
(k) Equipment purchased for a solar electric system or a paired solar and storage system must include a manufacturer warranty covering the following:
(A) The photovoltaic inverters for a minimum of five years against manufacturer’s defects
(B) Photovoltaic modules for a minimum of 20 years against degradation of performance below 80 percent of original output under standard test conditions
(l) All installations of a solar electric system or paired solar and storage system must include a total system workmanship warranty that covers the installation of solar panels, inverters, racking, patented roof protection systems, roof penetrations, batteries, electrical and mechanical parts, and wiring for the duration of at least five years.
(m) Any equipment installed as part of a solar electric system or paired solar and storage system must meet industry standards and the technical specifications provided in these rules.
(n) The solar electric system or paired solar and storage system must have received all applicable electrical and structural permits from the local jurisdiction and must pass all final inspections conducted by the authority having jurisdiction.
(o) The solar electric system or paired solar and storage system must follow electric utility-specific rules and regulations.
(p) The Total Solar Resource Fraction (“TSRF”) shall be calculated for each PV array and provided to the Department for reporting in the Department’s designated software system. All installations must meet the following minimum performance standards.
(A) For on-site shade analysis the TSRF must be 75 percent or greater at all points on the PV array.
(B) For remote shade analysis the TSRF must be 80 percent or greater for the roof plane where the PV array is located.
(C) The Department reserves the right to request documentation from a solar site analysis tool and to conduct independent verification of TSRF values.
(q) Under no circumstances will more than one rebate be issued under the program for the same solar electric system or paired solar and storage system.
(r) A solar electric system or paired solar and storage system installed for a low income service provider who is eligible under 330-240-0070 (Low-Income Service Provider Eligibility) paragraph (3) must be installed on a public building that provides social services to low- or moderate-income individuals, or provides emergency shelter and/or communications in disaster situations.

Source: Rule 330-240-0030 — Project Eligibility, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=330-240-0030.