OAR 340-210-0230
Notice of Construction and Approval of Plans: Notice to Construct


(1)

Any person proposing a Type 1 or 2 change must provide notice and applicable fees in OAR 340-216-8020 (Table 2 — Air Contaminant Discharge Permits) to DEQ before constructing or modifying a stationary source or air pollution control device. The notice must be in writing on a form supplied by DEQ and include the following information as applicable:

(a)

Name, address, and nature of business;

(b)

Name of local person responsible for compliance with these rules;

(c)

Name of person authorized to receive requests for data and information;

(d)

The type of construction or modification as defined in OAR 340-210-0220;

(e)

A description of the constructed or modified source;

(f)

A description of the production processes and a related flow chart for the constructed or modified source;

(g)

A plot plan showing the location and height of the constructed or modified source. The plot plan must also indicate the nearest residential or commercial property;

(h)

Type and quantity of fuels used;

(i)

The change in the amount, nature and duration of regulated pollutant emissions;

(j)

Plans and specifications for air pollution control devices and facilities and their relationship to the production process, including estimated efficiency of air pollution control devices under present or anticipated operating conditions;

(k)

Any information on pollution prevention measures and cross-media impacts the owner or operator wants DEQ to consider in determining applicable control requirements and evaluating compliance methods;

(l)

A list of any requirements applicable to the new construction or modification;

(m)

Where the operation or maintenance of air pollution control devices and emission reduction processes can be adjusted or varied from the highest reasonable efficiency and effectiveness, information necessary for DEQ to establish operational and maintenance requirements under OAR 340-226-0120 (Highest and Best Practicable Treatment and Control: Operating and Maintenance Requirements)(1) and (2); and

(n)

Amount and method of refuse disposal; and

(o)

Land Use Compatibility Statement signed by a local (city or county) planner either approving or disapproving construction or modification to the source if required by the local planning agency.

(2)

Any person proposing a Type 3 or 4 change must submit an application for either a construction ACDP, new permit, or permit modification, whichever is appropriate.

(3)

The owner of operator must notify DEQ of any corrections and revisions to the plans and specifications upon becoming aware of the changes.

(4)

Where a permit issued in accordance with OAR 340 divisions 216 or 218 includes construction approval for future changes for operational flexibility, the notice requirements in this rule are waived for the approved changes.
[NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040 (State of Oregon Clean Air Act Implementation Plan).]

Source: Rule 340-210-0230 — Notice of Construction and Approval of Plans: Notice to Construct, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-210-0230.