Alternative Regional Haze Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)


(1)

The owner and operator of the Foster-Wheeler boiler at the Boardman coal-fired power plant may elect to comply with OAR 340-223-0060 (Alternative BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) and 340-223-0070 (Additional NOx Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond), or with 340-223-0080 (Alternative Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Permanently Ceasing the Burning of Coal Within Five Years of EPA Approval of the Revision to the Oregon Clean Air Act State Implementation Plan Incorporating OAR Chapter 340, Division 223.), in lieu of complying with OAR 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)), if the owner or operator provides written notification to the Director by no later than July 1, 2014. The written notification must identify which rule of the two alternatives the owner or operator has chosen to comply with. The owner or operator may not change its chosen method of compliance after July 1, 2014.

(2)

Compliance with OAR 340-223-0080 (Alternative Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Permanently Ceasing the Burning of Coal Within Five Years of EPA Approval of the Revision to the Oregon Clean Air Act State Implementation Plan Incorporating OAR Chapter 340, Division 223.) in lieu of complying with 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) is allowed only if the Foster-Wheeler boiler at the Boardman coal-fired power plant permanently ceases to burn coal within five years of the approval by the United States Environmental Protection Agency (EPA) of the revision to the State of Oregon Clean Air Act Implementation Plan that incorporates OAR chapter 340, division 223. If the boiler has not permanently ceased burning coal by that date, the owner and operator shall be liable for violating OAR 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) for each day beginning July 1, 2014 on which the owner or operator did not comply with OAR 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)). This liability shall include, but is not limited to, civil penalties pursuant to OAR chapter 340, division 12, which includes penalties for the economic benefit of operating the facility without the required pollution controls.

(3)

If, by December 31, 2011, the EPA fails to approve a revision to the State of Oregon Clean Air Act Implementation Plan that incorporates OAR 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) (concerning BART requirements based upon permanently ceasing the burning of coal in the Foster-Wheeler Boiler by December 31, 2020), or 340-223-0060 (Alternative BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) and 340-223-0070 (Additional NOx Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond), then the compliance date of July 1, 2014 in 340-223-0060 (Alternative BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond)(2)(b) and (c) (sulfur dioxide and particulate matter emissions limits) is delayed until three years from the date of EPA approval.

(4)

Notwithstanding sections (1) and (3), if the EPA approves a revision to the State of Oregon Clean Air Act Implementation Plan that incorporates OAR 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) (concerning BART requirements based upon permanently ceasing the burning of coal in the Foster-Wheeler Boiler by December 31, 2020), then OAR 340-223-0060 (Alternative BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) and 340-223-0070 (Additional NOx Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) are repealed, compliance with 340-223-0060 (Alternative BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) and 340-223-0070 (Additional NOx Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Operation Until 2040 or Beyond) in lieu of complying with 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) is no longer an alternative, and compliance with 340-223-0030 (BART Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106)) or 340-223-0080 (Alternative Requirements for the Foster-Wheeler Boiler at the Boardman Coal-Fired Power Plant (Federal Acid Rain Program Facility ORISPL Code 6106) Based Upon Permanently Ceasing the Burning of Coal Within Five Years of EPA Approval of the Revision to the Oregon Clean Air Act State Implementation Plan Incorporating OAR Chapter 340, Division 223.) is required.
NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040 (State of Oregon Clean Air Act Implementation Plan).