OAR 340-245-0030
Submittal and Payment Deadlines


(1) When required to demonstrate compliance with OAR 340-245-0040 (Emissions Inventory), 340-245-0050 (Risk Assessment Procedures) or 340-245-0060 (Toxic Emissions Units), the owner or operator of a source must submit to DEQ all information and specific activity fees under OAR 340-216-8030 (Table 3 — Cleaner Air Oregon Specific Activity Fees) Table 3 required by, and by the deadlines specified in, subsections (a) through (j), as applicable, except as allowed under section (2). The owner or operator of a new or reconstructed source must also submit the following information but the time deadlines in subsections (a) through (j) do not apply.
(a)(A) An emissions inventory under OAR 340-245-0040 (Emissions Inventory) that will be used in the risk assessment must be submitted to DEQ no later than 90 days after the DEQ notice date; and
(B) For an existing source, if the owner or operator is submitting DEQ-approved source test data to supplement the emissions inventory, the updated emissions inventory must be submitted to DEQ no later than 150 days after the DEQ notice date. The owner or operator must also submit a modeling protocol and Level 3 or Level 4 Risk Assessment work plan prior to or concurrent with the submission of source test data, if applicable;
(b) The modeling protocol under OAR 340-245-0210 (Modeling and Risk Assessment Work Plan Requirements) must be submitted to DEQ no later than 30 days after receiving DEQ approval of the emissions inventory under subsection (a);
(c) The Level 3 or Level 4 Risk Assessment work plan under OAR 340-245-0210 (Modeling and Risk Assessment Work Plan Requirements) must be submitted to DEQ no later than 60 days after receiving DEQ approval of the updated emissions inventory under subsection (a);
(d) A Level 1 or Level 2 Risk Assessment under OAR 340-245-0050 (Risk Assessment Procedures)(8) or (9) must be submitted to DEQ no later than 60 days after DEQ approval of the modeling protocol required under subsection (b);
(e) A Level 3 Risk Assessment under OAR 340-245-0050 (Risk Assessment Procedures)(10) must be submitted to DEQ no later than 120 days after DEQ approval of the Level 3 Risk Assessment work plan required under subsection (c);
(f) A Level 4 Risk Assessment under OAR 340-245-0050 (Risk Assessment Procedures)(11) must be submitted to DEQ no later than 150 days after DEQ approval of the Level 4 Risk Assessment work plan required under subsection (c);
(g) If risk from the source is greater than the Immediate Curtailment Level, a report describing the immediate action taken by the owner or operator to reduce risk to below the Immediate Curtailment Level must be submitted to DEQ no later than seven days after DEQ approval of a Level 3 Risk Assessment or a Level 4 Risk Assessment under subsection (e) or (f);
(h) A Toxic Air Contaminant Monitoring Plan under OAR 340-245-0230 (Toxic Air Contaminant Monitoring Requirements) and an application for a Toxic Air Contaminant Permit Addendum under OAR 340-245-0100 (Toxic Air Contaminant Permit Addenda) must be submitted to DEQ no later than 30 days after DEQ approval of a Level 3 Risk Assessment or a Level 4 Risk Assessment under subsection (e) or (f);
(i) A Risk Reduction Plan under OAR 340-245-0130 (Risk Reduction Plan Requirements) and an application for a Toxic Air Contaminant Permit Addendum under OAR 340-245-0100 (Toxic Air Contaminant Permit Addenda) must be submitted to DEQ no later than 120 days after DEQ approval of a Level 3 or a Level 4 Risk Assessment under subsection (e) or (f); and
(j) For owners or operators that are not required to submit a Risk Reduction Plan and who do not choose to perform air monitoring, an application for a Toxic Air Contaminant Permit Addendum under OAR 340-245-0100 (Toxic Air Contaminant Permit Addenda) must be submitted to DEQ within 30 days after DEQ approval of any level of risk assessment, whichever is applicable.
(2) Upon receipt of a submittal described in section (1), DEQ will review the submittal and if DEQ determines that any additional information, corrections, or updates are required in order to approve the submittal, then DEQ will provide the owner or operator with a written request to provide such information by a date certain.
(3) An owner or operator may request an extension of time from a deadline established in section (1) or section (2) by providing DEQ with a written request no fewer than 15 days prior to the submittal deadline. DEQ may grant an extension based on the following criteria:
(a) The owner or operator has demonstrated progress in completing the submittal; and
(b) A delay is necessary, for good cause shown by the owner or operator, related to obtaining more accurate or new data, performing additional analyses, or addressing changes in operations or other key parameters, any of which are likely to have a substantive impact on the outcomes of the submittal.
(4) If DEQ determines it is not able to approve the owner or operator’s submittal, or if the owner or operator does not timely provide additional information or corrections requested by DEQ, then in addition to any other remedies available, DEQ may:
(a) With sufficient factual basis, modify the information provided by the owner or operator, approve it as modified, and the owner or operator must pay the document modification fee in OAR 340-216-8030 (Table 3 — Cleaner Air Oregon Specific Activity Fees) Table 3; or
(b) Inform the owner or operator of the deficiency, and provide the owner or operator with a revised deadline to submit the needed information.
(5) Recordkeeping. The owner or operator of a source that provides DEQ with any information related to a risk assessment completed under this rule must retain all of its records related to the risk assessment for five years from the date the information is submitted to DEQ.

Source: Rule 340-245-0030 — Submittal and Payment Deadlines, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-245-0030.

340‑245‑0005
Purpose and Overview
340‑245‑0010
Applicability and Jurisdiction
340‑245‑0020
Definitions
340‑245‑0022
Abbreviations and Acronyms
340‑245‑0030
Submittal and Payment Deadlines
340‑245‑0040
Emissions Inventory
340‑245‑0050
Risk Assessment Procedures
340‑245‑0060
Toxic Emissions Units
340‑245‑0100
Toxic Air Contaminant Permit Addenda
340‑245‑0110
Source Risk Limits
340‑245‑0120
Community Engagement
340‑245‑0130
Risk Reduction Plan Requirements
340‑245‑0140
Pollution Prevention
340‑245‑0150
Postponement of Risk Reduction
340‑245‑0200
Risk Estimates
340‑245‑0210
Modeling and Risk Assessment Work Plan Requirements
340‑245‑0220
TBACT and TLAER Procedures
340‑245‑0230
Toxic Air Contaminant Monitoring Requirements
340‑245‑0300
Toxicity Reference Values
340‑245‑0310
Process for Updating Lists of Regulated Toxic Air Contaminants and Their Risk-Based Concentrations
340‑245‑0320
Standards and Criteria for Noncancer Risk Action Levels for Existing Contamination Sources
340‑245‑0400
Cleaner Air Oregon Fees
340‑245‑8010
Table 1 - Risk Action Levels
340‑245‑8020
Table 2 - Toxic Air Contaminant Reporting List
340‑245‑8030
Table 3 - Toxicity Reference Values
340‑245‑8040
Table 4 - Risk-Based Concentrations
340‑245‑8050
Table 5 - Level 1 Risk Assessment Tool Dispersion Factors
340‑245‑9000
Colored Art Glass Manufacturing Facility Rules
340‑245‑9010
Colored Art Glass Manufacturing Facility Rules
340‑245‑9015
Colored Art Glass Manufacturing Facility Rules
340‑245‑9020
Colored Art Glass Manufacturing Facility Rules
340‑245‑9030
Colored Art Glass Manufacturing Facility Rules
340‑245‑9050
Colored Art Glass Manufacturing Facility Rules
340‑245‑9060
Colored Art Glass Manufacturing Facility Rules
340‑245‑9070
Colored Art Glass Manufacturing Facility Rules
340‑245‑9080
Colored Art Glass Manufacturing Facility Rules
Last Updated

Jun. 8, 2021

Rule 340-245-0030’s source at or​.us