OAR 345-023-0005
Need for a Facility
(1)
For electric transmission lines under the least-cost plan rule, OAR 345-023-0020 (Least-Cost Plan Rule)(1), or the system reliability rule for transmission lines, OAR 345-023-0030 (System Reliability Rule for Electric Transmission Lines), or by demonstrating that the transmission line is proposed to be located within a “National Interest Electric Transmission Corridor” designated by the U.S. Department of Energy under Section 216 of the Federal Power Act;(2)
For natural gas pipelines under the least-cost plan rule, OAR 345-023-0020 (Least-Cost Plan Rule)(1), or the economically reasonable rule for natural gas pipelines, OAR 345-023-0040 (Economically Reasonable Rule for Natural Gas Pipelines or Liquified Natural Gas Storage Facilities);(3)
For storage facilities for liquefied natural gas with storage capacity of three million gallons or greater under the least-cost plan rule, OAR 345-023-0020 (Least-Cost Plan Rule)(1), or the economically reasonable rule for liquefied natural gas storage facilities, OAR 345-023-0040 (Economically Reasonable Rule for Natural Gas Pipelines or Liquified Natural Gas Storage Facilities).
Source:
Rule 345-023-0005 — Need for a Facility, https://secure.sos.state.or.us/oard/view.action?ruleNumber=345-023-0005
.