OAR 409-024-0110
Capital Project Report


(1)

Each reporting entity must submit to the Authority a report of pending or proposed capital projects using a Capital Project Reporting Form CPR-1 as defined by the Authority. The report must be completed in accordance with instructions in the capital project reporting guidelines published on the Authority’s website.

(2)

The Capital Project Reporting Form CPR-1 shall include but is not limited to:

(a)

A summary of the information posted by the reporting entity under ORS 442.362 (Reporting of proposed capital projects by hospitals and ambulatory surgical centers).

(b)

The procedure that the reporting entity used to collect public comment.

(c)

A summary of expected community benefits for the project.

(d)

The estimated cost of the project.

(3)

Capital project reports must be submitted to the Authority no later than 30 days after financing for a project that has been approved for ambulatory surgical centers or within 30 days after the project has been approved by the hospital’s board of directors or other governing body for hospitals. The report shall be considered submitted on the date the report is postmarked or electronically delivered to the Authority, whichever is first.

(4)

The Authority shall maintain on its website a publicly available resource to enable interested parties to view capital project reports filed with the Authority.

Source: Rule 409-024-0110 — Capital Project Report, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=409-024-0110.

Last Updated

Jun. 8, 2021

Rule 409-024-0110’s source at or​.us