OAR 632-020-0105
Directional Drilling


(1)

The maximum point at which a well penetrates the producing formation must not vary from the vertical drawn from the center of the hole at the surface by more than 5 degrees. Deviation is permitted without special permission for short distances to straighten the hole, sidetrack junk, or to correct other mechanical difficulties.

(2)

Except for the purposes of straightening the hole, sidetracking junk, or correcting mechanical difficulties as provided in this rule, an operator may not drill a well that deviates from vertical unless the operator first files an application and obtains a permit from the department. If drilling is in progress, the operator must notify the department immediately of the deviation of the hole and file a written request with the department for approval, as required. If the department does not approve, the permittee must set a cement plug at the point of deviation from vertical and complete the well as originally approved or plug the well.

Source: Rule 632-020-0105 — Directional Drilling, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=632-020-0105.

632‑020‑0005
Jurisdiction and Authority
632‑020‑0010
Definitions
632‑020‑0015
Inspection and Supervision
632‑020‑0020
General Rules
632‑020‑0025
Supremacy of Special Rules
632‑020‑0028
Permit Required
632‑020‑0030
Application for Geothermal or Prospect Well
632‑020‑0031
Annual Permit Fees
632‑020‑0032
Permit Conditions
632‑020‑0035
Drilling Financial Security
632‑020‑0040
Assignment, Transfers of Ownership
632‑020‑0060
Filing of Well Records, Confidentiality
632‑020‑0065
Applications to Modify
632‑020‑0070
Well Designations
632‑020‑0090
Noise Abatement
632‑020‑0095
Casing Requirements
632‑020‑0100
Removal of Casings
632‑020‑0105
Directional Drilling
632‑020‑0110
Serving Orders
632‑020‑0115
Measurement of Geothermal Resources
632‑020‑0117
Spacing Plan
632‑020‑0120
Production Reports
632‑020‑0125
Proper Completion, Plugging, and Decommissioning
632‑020‑0130
Subsequent Decommissioning Report
632‑020‑0134
Naming of Fields
632‑020‑0135
Well Spacing
632‑020‑0138
Unit Agreements
632‑020‑0140
Commingling Production
632‑020‑0145
Pits or Sumps
632‑020‑0150
Disposal of Solid and Liquid Wastes
632‑020‑0151
Handling of Test Fluids
632‑020‑0154
Injection and Conservation
632‑020‑0155
Application to Inject
632‑020‑0156
Permit for Injection
632‑020‑0157
Injection Well Construction, Protection and Mechanical Integrity
632‑020‑0158
Wellhead Equipment, Injection Wells
632‑020‑0159
Monitoring Injection
632‑020‑0165
Judicial Review of Board Actions
632‑020‑0170
Environmental Protection
632‑020‑0175
Blowout Prevention for Geothermal Wells and Prospect Wells 2,000 Feet or More in Depth
632‑020‑0180
Blowout Prevention Rules for Prospect Wells Less than 2,000 Feet in Depth
Last Updated

Jun. 8, 2021

Rule 632-020-0105’s source at or​.us