OAR 632-037-0095
Permitting Agency Action on a Consolidated Application


(1)

Within 225 days of the issuance of a Notice to Proceed and not sooner than 60 days after the submittal of a complete environmental evaluation, each permitting agency shall submit to the Department its draft permit and permit conditions or permit denial document.

(2)

If a permitting agency includes in its draft permit a condition that is inconsistent with the environmental evaluation, the agency shall include with its draft permits a written explanation of the conditions setting forth the findings of the agency that support the condition.

Source: Rule 632-037-0095 — Permitting Agency Action on a Consolidated Application, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=632-037-0095.