OAR 660-003-0032
Expedited Review Upon Reconsideration or Consideration of a Subsequent Request for Acknowledgment


(1)

When the commission reconsiders an acknowledgment request pursuant to a continuance order, the commission may expedite the acknowledgment procedure by waiving, reducing or otherwise modifying the requirements of OAR 660-003-0010 (Acknowledgment Procedures), 660-003-0015 (Notice), and 660-003-0020 (Comments and Objections); provided, however, that notice will be provided to the local government, the coordination body, those persons who have submitted comments or objections on this portion of the acknowledgment request in accordance with the requirement of 660-003-0020 (Comments and Objections)(1) and (2), those persons who request notice in writing, and a general newspaper notice. Upon resubmittal such notice shall state that there is at least a 20 day period to be determined by the director for submission of written comments or objections from the mailing of the notice of the receipt of the acknowledgment request. However, in the judgment of the director, where continuances involve relatively complex issues, the notice shall provide the maximum notice possible, up to 45 days.

(2)

When the commission reconsiders an acknowledgment request subsequent to a continuance order; the commission shall expedite the acknowledgment procedure by relying on the previous record and limiting additional comments and objections, affected agency comments, and the department’s review to only those aspects of a city’s or county’s comprehensive plan or implementing ordinances previously identified by the commission as not being in compliance.

(3)

Upon receipt of corrections made pursuant to a continuance order submitted by a local government the department shall notify all persons who are entitled to notice of the local government’s acknowledgment request under section (1) of this rule, of the time and place where the corrections may be inspected and the time within which objections or comments to the corrections must be submitted.

(4)

Written comments or objections to the corrections made pursuant to a continuance order by the commission shall be submitted to the department in accordance with OAR 660-003-0020 (Comments and Objections).

(5)

The commission’s review of corrections made pursuant to a continuance order or the commission’s review of a new acknowledgment request made subsequent to a denial by the commission will be conducted in accordance with the requirements of OAR 660-003-0025 (Acknowledgment Review).

Source: Rule 660-003-0032 — Expedited Review Upon Reconsideration or Consideration of a Subsequent Request for Acknowledgment, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=660-003-0032.

Last Updated

Jun. 8, 2021

Rule 660-003-0032’s source at or​.us