OAR 731-017-0025
Additional Requirements for Time Extensions to Meet Funding Requirements


(1)

In addition to the requirements of section 0020 of this division, an application requesting an extension of time to meet the requirements of OAR 660-012-0060 (Plan and Land Use Regulation Amendments)(4)(b)(D) or 660-012-0060 (Plan and Land Use Regulation Amendments)(4)(c)(A) shall include the following additional information:

(a)

The additional time period being requested from the OTC, up to a maximum of 20 years from the date of application.

(b)

If applying for an extension of the time requirement in OAR 660-012-0060 (Plan and Land Use Regulation Amendments)(4)(c)(A), the identified mitigation improvements or measures for which a time extension is needed to avoid a significant adverse impact on the Interstate Highway system.

(c)

An explanation why OTC approval of a time extension is reasonable and necessary.

(d)

An explanation of what will be accomplished during the additional time period that makes compliance with OAR 660-012-0060 (Plan and Land Use Regulation Amendments)(1) likely by its conclusion.

(e)

A discussion of whether and how an extension of time might adversely impact other existing uses in the community or along a corridor.

(2)

Applications for time extensions beyond what is authorized in the OHP require OHP amendments and must be approved by the Commission. Pursuant to ODOT’s State Agency Coordination Agreement, any such amendment must comply with the coordination procedures in OAR 731-015-0065 (Coordination Procedures for Adopting Final Facility Plans).

Source: Rule 731-017-0025 — Additional Requirements for Time Extensions to Meet Funding Requirements, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=731-017-0025.