OAR 734-058-0070
Activity Details
(1)
The Applicant shall advise the DM’s office at least 48 hours in advance of commencing activity for which the Permit has been issued and within 48 hours of completion of the activity.(2)
The Applicant shall minimize the amount of debris, refuse and waste of all kinds on the highway Right of Way produced by activities of the Applicant. The Applicant shall remove any such debris, refuse or waste of any kind immediately upon completion of the activity, and restore the highway Right of Way to its pre-activity condition or better as determined by the DM.(3)
The Applicant shall minimize the amount of dirt or debris spread or tracked onto the highway from the activity area. The highway shall be cleaned of all dirt and debris at the end of each work day, or more frequently if so determined by the DM.(4)
The Applicant shall protect all existing highway features, including but not limited to the highway surface and structure, sidewalks and bicycle paths, bridges, signs, signals, pavement markers, guardrails and barriers, impact attenuators, drainage features, landscaping, and fences, from damage as a result of activity. The Applicant shall restore any damaged feature to the satisfaction of the DM whether discovered at the time of damage or at a later date. When planting is necessary to restore damaged landscape, the planting is subject to a plant establishment period of one year from the date of planting to ensure satisfactory growth of the planted materials. Unrepaired damage or unrestored features may be repaired or restored by the DM at the expense of the Applicant.(5)
Participation by or presence of individuals under 16 years of age at the activity site, other than in the regular pedestrian area of the roadway, is not allowed.
Source:
Rule 734-058-0070 — Activity Details, https://secure.sos.state.or.us/oard/view.action?ruleNumber=734-058-0070
.