A walkway conforming to OAR 741-320-0080 (Walkway Standard No. 1: Between Yards and Switches) (Standard No. 1), shall be constructed and maintained in a tunnel, upon order of the Department, only after notice to the affected railroad and hearing (in case of dispute), and be located as close as is possible to the tunnel wall, with its surface as close as possible to the top of ties.

(2)

At each end of a tunnel the walkway shall be gradually tapered in accordance with OAR 741-320-0070 (Slope) (slope) to meet the base of the ballast section or an existing walkway.

Source: Rule 741-320-0140 — Walkways in Tunnels, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=741-320-0140.

Last Updated

Jun. 8, 2021

Rule 741-320-0140’s source at or​.us