OAR 860-085-0650
Project Threshold


For the purpose of determining whether an application will be subjected to the procedural process described in either ORS 757.539 (Eligibility criteria)(6) or (7), Tier-1 and Tier-2 Projects are defined as follows:

(1)

A Tier-1 Project is one that has projected costs that would be borne by the ratepayers of the utility proposing the Project that are equal to or less than $1 million and has an overall project cost of less than $85 per metric ton of reduced emissions.

(2)

A Tier-2 Project is one that has projected costs that would be borne by the ratepayers of the utility proposing the Project that are greater than $1 million or has an overall project cost of equal to or greater than $85 per metric ton of reduced emissions.

Source: Rule 860-085-0650 — Project Threshold, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-085-0650 (accessed May 26, 2025).

May 26, 2025

Rule 860-085-0650's source at or​.us