OAR 860-087-0040
Transportation Electrification Program Reporting Requirements


(1)

An electric company must report the results of its evaluation for each Transportation Electrification Program approved by the Commission. A program evaluation must include, but is not limited to:

(a)

The information required under OAR 860-087-0030 (Transportation Electrification Program Application Requirements)(1)(g)(A)-(F);

(b)

An assessment of program costs and benefits realized by ratepayers and the electric company;

(c)

A tracking of program costs over the life of the program;

(d)

Progress against identified market barriers and implementation barriers;

(e)

Current risk that investment will result in stranded costs;

(f)

Whether any program modifications are recommended to help meet expected outcomes;

(g)

Updated market data, including a description of changes in the condition of the transportation electrification market within the electric company’s service territory; and

(h)

An evaluation of whether and how the program has:

(A)

Accelerated transportation electrification;

(B)

Stimulated innovation, competition, and customer choice; and

(C)

Supported system efficiency and operational flexibility, including the ability to integrate variable resources.

(2)

The Commission may request additional program updates, including milestones and progress against success indicators, to assess whether to continue, discontinue, or modify approved Transportation Electrification Programs.

Source: Rule 860-087-0040 — Transportation Electrification Program Reporting Requirements, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-087-0040.

Last Updated

Jun. 8, 2021

Rule 860-087-0040’s source at or​.us