ORS 197A.513
Plan amendments

  • approvals
  • petition for writ of mandamus

(1)

The state, Metro, all affected local governments and any affected special districts and political subdivisions shall:

(a)

Amend their comprehensive, functional or regional framework plans, including public facility plans, transportation system plans and all applicable land use regulations, as necessary to be consistent with a land use final order adopted under ORS 197A.509 (Development of land use final order) and 197A.511 (Land use final order); and

(b)

Issue the appropriate development approval, permit, license, certificate or other approval necessary for the construction of the project or project improvements to implement a land use final order as necessary to avoid significantly delaying the completion or implementation of the project. Development approvals, permits, licenses, certificates or other approvals may be subject only to reasonable and necessary conditions of approval but those conditions may not, by themselves or cumulatively, prevent implementation of a land use final order.

(2)

For the purposes of subsection (1)(b) of this section:

(a)

An approval condition is not reasonable or necessary, or is considered to prevent implementation of a land use final order, if the approval condition applies to a measure, improvement or development that:

(A)

Is not included in the scope of the project in the Full Funding Grant Agreement;

(B)

Does not qualify for federal New Starts funding pursuant to 49 U.S.C. 5309;

(C)

Is not physically and functionally necessary for the project; or

(D)

The steering committee established under ORS 197A.509 (Development of land use final order) has determined:
(i)
To be infeasible using the federal, state and local funds within the project budget;
(ii)
Will significantly delay the completion or otherwise prevent the timely implementation of the project; or
(iii)
Will have a significant negative impact on the operations of the project.

(b)

In the event that a land use approval is delayed causing significant delay of the completion or implementation of the project, TriMet may pursue any remedy available in law or equity. Not less than 10 days prior to commencing an action for relief under this section, TriMet shall provide written notice to each local government to which TriMet submitted an application for a land use decision relating to the project.

(3)

Intentionally left blank —Ed.

(a)

If the state, Metro or an affected local government, special district or political subdivision does not take final action on an application for a development approval, permit, license, certificate or other approval as required under subsection (1) of this section, TriMet may file a petition for a writ of mandamus according to the procedures for cities described in ORS 227.179 (Petition for writ of mandamus authorized when city fails to take final action on land use application within 120 days).

(b)

Notwithstanding ORS 227.179 (Petition for writ of mandamus authorized when city fails to take final action on land use application within 120 days) (5), the court shall issue a peremptory writ unless the governing body or any intervenor shows that the approval would violate the criteria adopted by the Land Conservation and Development Commission under ORS 197A.505 (Establishment of criteria for decisions in land use final order).

(4)

Each affected local government, special district or political subdivision that issues a development approval, permit, license, certificate or other approval for the project under subsection (1)(b) of this section shall continue to exercise enforcement authority over the development approval, permit, license, certificate or other approval.

(5)

An amendment to the plan or a land use regulation required under subsection (1)(a) of this section is not subject to review by any court or agency.

(6)

Intentionally left blank —Ed.

(a)

Development approvals issued under subsection (1)(b) of this section shall be treated as land use decisions, but not as limited land use decisions.

(b)

Development approvals, permits, licenses, certificates and other approvals issued under subsection (1)(b) of this section may be the subject of administrative and judicial review as provided by law.

(7)

Steering committee determinations made under subsection (2)(a)(D) of this section shall control in the event of a conflict and are not subject to review. [2017 c.714 §8]
Note: See note under 197A.500 (Definitions for ORS 197A.500 to 197A.521).

Source: Section 197A.513 – Plan amendments; approvals; petition for writ of mandamus, https://www.­oregonlegislature.­gov/bills_laws/ors/ors197A.­html (accessed May 26, 2025).

197A.015
Definitions for ORS 197.475 to 197.493 and ORS chapter 197A
197A.018
Definition of “needed housing.”
197A.020
Limitations on requiring contribution for government assisted housing
197A.025
Policy
197A.030
Department support to local governments to incentivize needed housing
197A.100
Housing production strategy
197A.103
Review of housing production strategy
197A.110
City report on housing permitting and production
197A.115
City report on implementation of housing production strategy
197A.130
Identification of cities with unmet housing needs
197A.200
Local government planning for needed housing
197A.205
Housing and Community Services Department review of certain local housing measures
197A.210
Development-ready lands
197A.215
Application to remove property from within urban growth boundary
197A.230
Definitions for ORS 197A.230 to 197A.250
197A.232
Findings regarding long-range planning
197A.235
Designation of rural and urban reserves pursuant to intergovernmental agreement
197A.242
Coordinated and concurrent process for designation of urban and rural reserves
197A.245
Urban reserves
197A.250
Designation of certain Washington County lands
197A.270
Determination of housing capacity and accommodation of needed housing by cities with population of 25,000 or greater
197A.278
Lane County accommodation of needed housing
197A.280
Determination of housing capacity and accommodation of needed housing by cities with population of less than 25,000
197A.285
Priority of land to be included within urban growth boundaries
197A.300
Definition of “serviceable.”
197A.302
Purposes
197A.305
Alternative amendment process
197A.310
Cities with population of less than 10,000
197A.312
Cities with population of 10,000 or greater
197A.315
Expansion study areas
197A.325
Review of final decision of city
197A.335
Determination of housing capacity and accommodation of needed housing by Metro cities
197A.348
Definition of “needed housing.”
197A.350
Determination of housing capacity and accommodation of needed housing by Metro
197A.355
Priority of land to be included within Metro urban growth boundary
197A.358
Metro urban growth boundary designation
197A.362
Timing of Metro accommodation of needed housing
197A.365
Metro housing coordination strategy
197A.370
Metro report of performance measures
197A.372
Metro evaluation of accommodation of needed housing
197A.395
Limits on local government prohibitions
197A.400
Clear and objective approval criteria required
197A.420
Duplexes
197A.425
Accessory dwelling units
197A.430
Single room occupancies
197A.445
Affordable housing allowed outright
197A.460
Residential use of commercial lands for affordable housing
197A.465
Local requirements to develop affordable housing
197A.470
Final action on affordable housing application
197A.500
Definitions for ORS 197A.500 to 197A.521
197A.502
Legislative findings
197A.503
Preemptive effect of ORS 197A.500 to 197A.521
197A.505
Establishment of criteria for decisions in land use final order
197A.507
Procedure for review of established criteria
197A.509
Development of land use final order
197A.511
Land use final order
197A.513
Plan amendments
197A.515
Land Use Board of Appeals review of land use final order
197A.517
Supreme Court review of Land Use Board of Appeals opinion on land use final order
197A.519
Amendments to land use final order
197A.521
Failure to meet timeline

Current through early 2026

§ 197A.513. Plan amendments's source at oregon​.gov