ORS 469A.120
Cost recovery by electric companies


(1)

Except as provided in ORS 469A.180 (Electric companies) (5), all prudently incurred costs associated with complying with ORS 469A.005 (Definitions for ORS 469A.005 to 469A.210) to 469A.210 (Goal for community-based renewable energy projects) are recoverable in the rates of an electric company, including interconnection costs, costs associated with using physical or financial assets to integrate, firm or shape renewable energy sources on a firm annual basis to meet retail electricity needs, above-market costs and other costs associated with transmission and delivery of qualifying electricity to retail electricity consumers.

(2)

Intentionally left blank —Ed.

(a)

The Public Utility Commission shall establish an automatic adjustment clause as defined in ORS 757.210 (Hearing to establish new schedules) or another method that allows timely recovery of costs prudently incurred by an electric company to construct or otherwise acquire facilities that generate electricity from renewable energy sources, costs related to associated electricity transmission and costs related to associated energy storage.

(b)

Notwithstanding any other provision of law, upon the request of any interested person the commission shall conduct a proceeding to establish the terms of the automatic adjustment clause or other method for timely recovery of costs. The commission shall provide parties to the proceeding with the procedural rights described in ORS 756.500 (Complaint) to 756.610 (Judicial review), including but not limited to the opportunity to develop an evidentiary record, conduct discovery, introduce evidence, conduct cross-examination and submit written briefs and oral argument. The commission shall issue a written order with findings on the evidentiary record developed in the proceeding.

(3)

Intentionally left blank —Ed.

(a)

An electric company must file with the commission for approval of a proposed rate change to recover costs under the terms of an automatic adjustment clause or other method for timely recovery of costs established under subsection (2) of this section. As part of an electric company’s request for approval under this subsection, the electric company may specify the date or the dates on which the electric company will begin to include in the electric company’s rates, in full or in part, the costs recoverable under subsection (2) of this section. The commission may accept or reject the date or dates specified by the electric company.

(b)

Notwithstanding any other provision of law, upon the request of any interested person the commission shall conduct a proceeding to determine whether to approve a proposed change in rates under the automatic adjustment clause or other method for timely recovery of costs. The commission shall provide parties to the proceeding with the procedural rights described in ORS 756.500 (Complaint) to 756.610 (Judicial review), including but not limited to the opportunity to develop an evidentiary record, conduct discovery, introduce evidence, conduct cross-examination and submit written briefs and oral argument. The commission shall issue a written order with findings on the evidentiary record developed in the proceeding.

(c)

A filing made under this subsection is subject to the commission’s authority under ORS 757.215 (Commission authorized to suspend new rates or order interim rates during hearings) to suspend a rate, or schedule of rates, for investigation. [2007 c.301 §13; 2010 c.79 §1; 2016 c.28 §11]

Source: Section 469A.120 — Cost recovery by electric companies, https://www.­oregonlegislature.­gov/bills_laws/ors/ors469A.­html.

469A.005
Definitions for ORS 469A.005 to 469A.210
469A.010
Qualifying electricity
469A.020
Qualifying electricity
469A.025
Renewable energy sources
469A.027
Certification of eligibility for certain generating facilities
469A.029
Eligibility
469A.031
Eligibility
469A.050
Applicable standard
469A.052
Large utility renewable portfolio standard
469A.055
Small electric utilities
469A.060
Exemptions from compliance with renewable portfolio standard
469A.065
Renewable portfolio standard for electricity service suppliers
469A.070
Manner of complying with renewable portfolio standards
469A.075
Implementation plan for electric companies
469A.100
Limits on cost of compliance with renewable portfolio standard
469A.120
Cost recovery by electric companies
469A.130
Renewable energy certificates system
469A.132
Thermal renewable energy certificates
469A.135
Renewable energy certificates that may be used to comply with standards
469A.140
Use, transfer and banking of certificates
469A.145
Limitations on use of unbundled certificates to meet renewable portfolio standard
469A.147
Exemption from limitation on use of unbundled certificates for consumer-owned utilities
469A.150
Multistate electric companies
469A.170
Compliance reports
469A.180
Electric companies
469A.185
Consumer-owned utilities
469A.200
Penalty
469A.205
Green power rate
469A.210
Goal for community-based renewable energy projects
469A.300
Hydrogen power stations
469A.400
Definitions for ORS 469A.400 to 469A.475
469A.405
Policy
469A.410
Clean energy targets
469A.415
Electric companies to develop clean energy plans
469A.420
Emissions verification
469A.425
Community advisory group
469A.430
Treatment of generation resources
469A.435
Determining compliance with clean energy targets
469A.440
Temporary exemption
469A.445
Cost cap for electric companies
469A.450
Cost cap for electricity service suppliers
469A.455
Performance incentive for early compliance
469A.460
No modification to renewable portfolio standards
469A.465
Rules
469A.475
Legislative findings
469A.480
Electric company serving 25,000 or fewer consumers not subject to requirements
Green check means up to date. Up to date