OAR 141-085-0545
Fees; Amounts and Disposition


(1)

Disposition of Fees. All applications that require a fee, except for an emergency authorization, must include the fee at the time of application.

(2)

Project Applications that Require a Fee. Except as provided in Section (3) of this rule, the following types of projects require a fee for a complete application:

(a)

Individual Permit and General Permit applications that require a fee, must be accompanied by the applicable base fee and volume fee in accordance with the current fee schedule;

(b)

General Authorization notifications which require a fee under OAR 141-089-0635 (Fees; Disposition of Fees), must be accompanied by the flat fee when the proposed removal-fill activity is 50 cubic yards or more; and

(c)

Emergency Authorization holders, except for erosion or flood repair, must submit the required fee to the Department within 45 calendar days of receiving the authorization.

(3)

Project Applications that Do Not Require a Fee. No application fee or renewal fee is required when submitting an application or notification for the following:

(a)

An agency determination that the project does not require a permit from the Department;

(b)

Erosion-flood repair or stream bank stabilization projects, regardless of the authorization type;

(c)

Voluntary habitat restoration projects directed at habitat improvement, regardless of the authorization type;

(d)

A general authorization when the project involves less than 50 cubic yards of removal-fill activity; and

(e)

A general permit that does not require a fee when specified in OAR 141-093.

(4)

Calculating Application Fees. For each application that involves both removal and fill activity, the application fee is calculated separately for each activity using the base and volume fees. The required fee to be submitted with the application is the greater of the two calculated fees.

(5)

Base Fees. Base fees are based on the following applicant classifications:

(a)

Private operator, or a person contracting to perform services for a private operator;

(b)

Public body; or

(c)

Commercial operator.

(6)

Volume Fees. In addition to the base fee established under Section (5) of this rule, each applicant may be required to also pay, as part of the application, an additional fee based on the volume of material according to the following schedule:

(a)

Less than 500 cubic yards;

(b)

500 to less than 5,000 cubic yards;

(c)

5,000 to less than or equal to 50,000 cubic yards; or

(d)

Over 50,000 cubic yards.

(7)

Annual fees. For individual permits that are renewed or valid for more than one year, an annual fee is assessed for each year that the permit is in effect. The annual fee is equal to the base fee at the time of renewal or annual billing and is due by the anniversary date of issuance of the permit.

(8)

Multiyear Permits. For issuance of multiyear permits valid over a period of more than one year and up to five years, the Department may assess a one-time fee at the rate in effect at the time of the application or renewal. The one-time fee must include:

(a)

The application fee; and

(b)

Any applicable annual fees for the duration of the term of the permit.

(9)

Adjusting Fee Amounts. Fees are adjusted annually, on January 1 of each year. By December 1 of each year the Department will consult the Portland-Salem, OR-WA Consumer Price Index for All Urban Consumers for All Items as published by the Bureau of Labor Statistics of the United States Department of Labor to determine the appropriate annual fee adjustment to become effective on January 1 of the following year. The Department will then revise the fees in accordance with the CPI and post the fee schedule on the Department’s website (http://oregonstatelands.us/).

Source: Rule 141-085-0545 — Fees; Amounts and Disposition, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-085-0545.

141‑085‑0500
General
141‑085‑0506
Policy
141‑085‑0510
Definitions
141‑085‑0515
Removal-Fill Jurisdiction by Type of Water
141‑085‑0520
Removal-Fill Jurisdiction by Volume of Material
141‑085‑0525
Measuring and Calculating Volume of Removal and Fill
141‑085‑0530
Exemptions for Certain Activities and Structures
141‑085‑0534
Exemptions for Certain Voluntary Habitat Restoration Activities
141‑085‑0535
Exemptions Specific to Agricultural Activities
141‑085‑0540
Types of Authorizations
141‑085‑0545
Fees
141‑085‑0550
Application Requirements for Individual Permits
141‑085‑0555
Individual Removal-Fill Permit Application Review Process
141‑085‑0560
Public Review Process for Individual Removal - Fill Permit Applications
141‑085‑0565
Department Determinations and Considerations in Evaluating Individual Permit Applications
141‑085‑0575
Permit Appeals
141‑085‑0580
Discovery in Contested Cases
141‑085‑0585
Permit Conditions, Permit Expiration Dates and Permit Transfer
141‑085‑0590
Renewal and Extension of Individual Removal-Fill Permits
141‑085‑0595
Permit Requirements and Interagency Coordination for Department of Environmental Quality Approved Remedial Action, Corrections Facilities, Solid Waste Land Fills and Energy Facilities
141‑085‑0665
Expedited Process for Industrial or Traded Sector Sites
141‑085‑0676
Emergency Authorizations
141‑085‑0680
Compensatory Mitigation (CM)
141‑085‑0685
Functions and Values Assessment
141‑085‑0690
Eligibility Requirements for CM
141‑085‑0692
Mitigation Accounting
141‑085‑0694
Special Requirement for CM
141‑085‑0695
Administrative Protection of CM Sites
141‑085‑0700
Financial Security for CM Sites
141‑085‑0705
Requirements for CM Plans
141‑085‑0710
Monitoring Requirements for CWM
141‑085‑0715
Mitigation for Temporary Impacts
141‑085‑0720
Mitigation Banking Purpose, Applicability and Policies
141‑085‑0725
Process for Establishing Mitigation Banks
141‑085‑0730
Establishment of Mitigation Credits
141‑085‑0735
Release, Use and Sale of Mitigation Credits
141‑085‑0740
Authorization for Mitigation Banks
141‑085‑0745
In-Lieu Fee Mitigation
141‑085‑0750
Payments to and Expenditures from the Oregon Removal-Fill Mitigation Fund
141‑085‑0755
Advance Mitigation
141‑085‑0768
Advance Aquatic Resource Plans
141‑085‑0770
Complaints and Investigations
141‑085‑0775
Enforcement Actions and Procedures
141‑085‑0780
Revoking or Suspending an Authorization
141‑085‑0785
Civil Penalties
Last Updated

Jun. 8, 2021

Rule 141-085-0545’s source at or​.us