(1) Purpose and Applicability. These rules describe the requirements to establish and operate mitigation banks, which can be used to compensate for impacts to waters of this state. These rules pertain to mitigation banks that compensate for impacts to all types of waters of this state.
(2) Coordination with the Corps of Engineers. The Department will coordinate with and participate on the Interagency Review Team as a co-chair agency with the Corps of Engineers to establish mitigation banks that also meet the federal regulatory requirements, as appropriate.
(3) Development of Mitigation Banks is Encouraged. The Department encourages the development and will facilitate the expeditious approval of mitigation banks.
(4) Compensation for Expected or Historical Losses to Aquatic Resources. Mitigation banks must be located and designed to compensate for expected or historical losses to aquatic resources by:
(a) Maintaining regional functions and values of aquatic resources in their service area;
(b) Matching the demand for credits with losses to the water resources of this state; and
(c) Meeting other ecological or watershed needs as determined by the Department.
(5) Banks Must Meet Principal Objectives for CM: Mitigation banks established and operated under these rules must meet the principal objectives of compensatory mitigation in OAR 141-085-0680 (Compensatory Mitigation (CM); Applicability and Principal Objectives).
(6) Subject to All CM Rules. Mitigation banks are subject to all rules governing CWM and CNWM, as applicable.
(7) Collaboration with Public Resource Protection and Restoration Programs. The Department encourages collaboration with voluntary watershed enhancement projects in conjunction with, but supplemental to, the generation of compensatory mitigation credit, when greater ecological gains can be recognized. Except where public funding is specifically authorized to provide compensatory mitigation, or the Department otherwise approves the use or accounting of such funds, funds dedicated to non-compensatory aquatic resource restoration or preservation projects will not generate transferable mitigation credit.

Source: Rule 141-085-0720 — Mitigation Banking Purpose, Applicability and Policies, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=141-085-0720.

141‑085‑0500
General
141‑085‑0506
Policy
141‑085‑0510
Definitions
141‑085‑0515
Removal-Fill Jurisdiction by Type of Water
141‑085‑0520
Removal-Fill Jurisdiction by Volume of Material
141‑085‑0525
Measuring and Calculating Volume of Removal and Fill
141‑085‑0530
Exemptions for Certain Activities and Structures
141‑085‑0534
Exemptions for Certain Voluntary Habitat Restoration Activities
141‑085‑0535
Exemptions Specific to Agricultural Activities
141‑085‑0540
Types of Authorizations
141‑085‑0545
Fees
141‑085‑0550
Application Requirements for Individual Permits
141‑085‑0555
Individual Removal-Fill Permit Application Review Process
141‑085‑0560
Public Review Process for Individual Removal - Fill Permit Applications
141‑085‑0565
Department Determinations and Considerations in Evaluating Individual Permit Applications
141‑085‑0575
Permit Appeals
141‑085‑0580
Discovery in Contested Cases
141‑085‑0585
Permit Conditions, Permit Expiration Dates and Permit Transfer
141‑085‑0590
Renewal and Extension of Individual Removal-Fill Permits
141‑085‑0595
Permit Requirements and Interagency Coordination for Department of Environmental Quality Approved Remedial Action, Corrections Facilities, Solid Waste Land Fills and Energy Facilities
141‑085‑0665
Expedited Process for Industrial or Traded Sector Sites
141‑085‑0676
Emergency Authorizations
141‑085‑0680
Compensatory Mitigation (CM)
141‑085‑0685
Functions and Values Assessment
141‑085‑0690
Eligibility Requirements for CM
141‑085‑0692
Mitigation Accounting
141‑085‑0694
Special Requirement for CM
141‑085‑0695
Administrative Protection of CM Sites
141‑085‑0700
Financial Security for CM Sites
141‑085‑0705
Requirements for CM Plans
141‑085‑0710
Monitoring Requirements for CWM
141‑085‑0715
Mitigation for Temporary Impacts
141‑085‑0720
Mitigation Banking Purpose, Applicability and Policies
141‑085‑0725
Process for Establishing Mitigation Banks
141‑085‑0730
Establishment of Mitigation Credits
141‑085‑0735
Release, Use and Sale of Mitigation Credits
141‑085‑0740
Authorization for Mitigation Banks
141‑085‑0745
In-Lieu Fee Mitigation
141‑085‑0750
Payments to and Expenditures from the Oregon Removal-Fill Mitigation Fund
141‑085‑0755
Advance Mitigation
141‑085‑0768
Advance Aquatic Resource Plans
141‑085‑0770
Complaints and Investigations
141‑085‑0775
Enforcement Actions and Procedures
141‑085‑0780
Revoking or Suspending an Authorization
141‑085‑0785
Civil Penalties
Last Updated

Jun. 8, 2021

Rule 141-085-0720’s source at or​.us