OAR 340-244-0238
Emission Standards for Gasoline Dispensing Facilities: Compliance Dates


(1)

For a new or reconstructed affected source, the owner or operator must comply with the standards in OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements) and 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements), as applicable, no later than Jan. 10, 2008 or upon startup, whichever is later, except as follows:

(a)

The owner or operator of a new or reconstructed GDF must comply with OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements)(1)(b) and (c) no later than July 1, 2009 or upon startup, whichever is later.

(b)

For tanks located at a GDF with average monthly throughput of less than 10,000 gallons of gasoline, the owner or operator must comply with the standards in OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements)(3) no later than Dec. 13, 2009.

(c)

For tanks located at a GDF with average monthly throughput less than 100,000 gallons of gasoline and not listed in OAR 340-244-0234 (Emission Standards for Gasoline Dispensing Facilities: Affected Sources)(4)(a)(C) or (4)(b), must comply with 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements), as applicable, no later than Dec. 13, 2009 or upon startup, whichever is later.

(d)

The owner or operator of a GDF subject to Table 2 of OAR 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements) must comply no later than Sep. 23, 2008 or upon startup, whichever is later.

(2)

For an existing affected source, the owner or operator must comply with the standards in OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements) and 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements), as applicable, by no later than Jan. 10, 2011, except as follows:

(a)

For tanks with a capacity between 1,500 and 40,000 gallons and located in the Portland AQMA, Medford AQMA, or Salem SATS, the owner or operator must comply with the standards in OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements)(3) and 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements) no later than Dec. 13, 2008.

(b)

For tanks located at an affected source located in Clackamas, Multnomah, or Washington County, whose annual throughput exceeds 120,000 gallons, the owner or operator must comply with the standards in OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements)(3) and 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements) no later than Dec. 13, 2008.

(c)

The owner or operator of an existing GDF must comply with OAR 340-244-0240 (Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements)(1)(b) and (c) no later than July 1, 2009 or upon startup, whichever is later.

(3)

For an existing affected source that becomes subject to the control requirements in OAR 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements) because of an increase in the monthly throughput, as specified in 340-244-0234 (Emission Standards for Gasoline Dispensing Facilities: Affected Sources)(4), the owner or operator must comply with the standards 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements) no later than 3 years after the affected source becomes subject to the control requirements in 340-244-0242 (Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements).

(4)

The initial compliance demonstration test required under OAR 340-244-0244 (Emission Standards for Gasoline Dispensing Facilities: Testing and Monitoring Requirements)(1)(a) and (b) must be conducted as specified in subsections (4)(a) and (b).

(a)

For a new or reconstructed affected source, the owner or operator must conduct the initial compliance test upon installation of the complete vapor balance system.

(b)

For an existing affected source, the owner or operator must conduct the initial compliance test as specified in paragraph (4)(b)(A) or (B) of this rule.

(A)

For vapor balance systems installed on or before Dec. 15, 2009 at a GDF whose average monthly throughput is 100,000 gallons of gasoline or more, the owner or operator must test no later than 180 days after the applicable compliance date specified in section (2) or (3).

(B)

For vapor balance systems installed after Dec. 15, 2009, the owner or operator must test upon installation of a complete vapor balance system or a new gasoline storage tank.

(C)

For a GDF whose average monthly throughput is less than or equal to 100,000 gallons of gasoline, the owner or operator is only required to test upon installation of a complete vapor balance system or a new gasoline storage tank.

(5)

If the GDF is subject to the control requirements in OAR 340-244-0232 (Emission Standards for Gasoline Dispensing Facilities: Purpose) through 340-244-0252 (Emission Standards for Gasoline Dispensing Facilities: General Provision Applicability) only because it loads gasoline into fuel tanks other than those in motor vehicles, as defined in 340-244-0030 (General Provisions for Stationary Sources: Definitions), the owner or operator of the GDF must comply with the standards in 340-244-0232 (Emission Standards for Gasoline Dispensing Facilities: Purpose) through 340-244-0252 (Emission Standards for Gasoline Dispensing Facilities: General Provision Applicability) as specified in subsections (5)(a) and (b).

(a)

If the GDF is an existing facility, the owner or operator of the GDF must comply by Jan. 24, 2014.

(b)

If the GDF is a new or reconstructed facility, the owner or operator of the GDF must comply by the dates specified in paragraphs (5)(b)(A) and (B).

(A)

If startup of the GDF is after Dec. 15, 2009, but before January 24, 2011, the owner or operator of the GDF must comply no later than Jan. 24, 2011.

(B)

If startup of the GDF is after Jan. 24, 2011, the owner or operator of the GDF must comply upon startup of the GDF.
NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040 (State of Oregon Clean Air Act Implementation Plan).
[ED. NOTE: Tables referenced are available from the agency.]

Source: Rule 340-244-0238 — Emission Standards for Gasoline Dispensing Facilities: Compliance Dates, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-244-0238.

340–244–0010
General Provisions for Stationary Sources: Policy and Purpose
340–244–0020
General Provisions for Stationary Sources: Delegation of Authority
340–244–0030
General Provisions for Stationary Sources: Definitions
340–244–0040
General Provisions for Stationary Sources: List of Hazardous Air Pollutants
340–244–0050
General Provisions for Stationary Sources: Amending the List of Hazardous Air Pollutants
340–244–0100
Compliance Extensions for Early Reductions: Applicability
340–244–0200
Compliance Extensions for Early Reductions: Emissions Limitation for New and Reconstructed Major Sources
340–244–0210
Emission Standards: Emissions Limitation for Existing Sources
340–244–0220
Emission Standards: Federal Regulations Adopted by Reference
340–244–0232
Emission Standards for Gasoline Dispensing Facilities: Purpose
340–244–0234
Emission Standards for Gasoline Dispensing Facilities: Affected Sources
340–244–0236
Emission Standards for Gasoline Dispensing Facilities: Affected Equipment or Processes
340–244–0238
Emission Standards for Gasoline Dispensing Facilities: Compliance Dates
340–244–0239
Emission Standards for Gasoline Dispensing Facilities: General Duties to Minimize Emissions
340–244–0240
Emission Standards for Gasoline Dispensing Facilities: Work Practice and Submerged Fill Requirements
340–244–0242
Emission Standards for Gasoline Dispensing Facilities: Vapor Balance Requirements
340–244–0244
Emission Standards for Gasoline Dispensing Facilities: Testing and Monitoring Requirements
340–244–0246
Emission Standards for Gasoline Dispensing Facilities: Notifications
340–244–0248
Emission Standards for Gasoline Dispensing Facilities: Recordkeeping Requirements
340–244–0250
Emission Standards for Gasoline Dispensing Facilities: Reporting Requirements
340–244–0252
Emission Standards for Gasoline Dispensing Facilities: General Provision Applicability
Last Updated

Jun. 8, 2021

Rule 340-244-0238’s source at or​.us