OAR 345-095-0045
Construction Reports


(1)

Prior to the initial production of yellowcake, the site certificate holder shall submit copies of monthly construction progress reports to the Council. Such reports shall describe the status of mining activities, building construction and tailings dam and pond construction in sufficient detail to allow the Council or its representatives to observe significant construction progress.

(2)

The certificate holder shall notify the Council of any major changes in construction schedules and of any significant changes in process equipment, pollution control equipment or facilities or equipment or facilities designed for the protection of workers.