OAR 603-100-0030
Submission of Plans


(1)

Plans for a new shellfish plant or storage facility construction or existing plant remodeling shall be submitted to the Department for review and approval at least 90 days prior to actual construction.

(2)

Plans shall be submitted as blue-prints, photostats, or original drawing using India ink on substantial drawing paper. The following information shall be included in the plans:

(a)

Plot plan of grounds on which building is to be constructed or addition is to be located showing size of area and boundaries;

(b)

Floor and elevation plans drawn to scale showing the accurate location of equipment;

(c)

Specifications and design detail of equipment, location of plumbing fixtures, and materials used in all processing and storage areas;

(d)

If a privately owned public water system is used, plans meeting the specifications of OAR 333-061-0005 (Purpose) through 333-061-0095 (Severability), Public Water Systems, must be submitted to and approved by the appropriate agency.