OAR 690-052-0020
Initiation of Decommissioning Process


(1)

If an operator does not submit a notice of intent to reauthorize under ORS 543A.030, the Department shall within 60 days after the deadline for filing the Notice of Intent, request from the operator information regarding the decommissioning of the project pursuant to 543A.030(2), if the information has not already been filed. If the Department is unable to contact the operator, the Department may proceed with the decommissioning process, complying with the provisions of this chapter, as practical, in the absence of the operator.

(2)

The Department does not have to initiate the decommissioning process upon receipt of the information requested in subsection (1) of this section. However, the Department shall initiate the decommissioning process at least one year prior to the expiration of the project’s license.

Source: Rule 690-052-0020 — Initiation of Decommissioning Process, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=690-052-0020.

Last Updated

Jun. 8, 2021

Rule 690-052-0020’s source at or​.us