OAR 690-052-0040
Process Determination


(1)

After the close of the comment period in OAR 690-052-0030 (Public Notice and Comment), the Department shall determine whether the decommissioning plan will be developed through a standard or expedited process. In making the determination, the Department shall consider any information received from the operator, comments received from agencies and the public pursuant to 690-052-0030 (Public Notice and Comment), and the following guidelines:

(a)

The expedited process shall be used for projects without dams or other permanent structures in the stream, projects which use pipes or other easily removable works to divert or withdraw water from the stream.

(b)

The standard process shall be used for projects using dams or other large permanent structures in the stream to create a reservoir or divert water.

(2)

Not withstanding subsection (1) of this section, upon good cause, the Department may deviate from the guidelines in subsection (1) of this section when determining which decommissioning process to use.

(3)

The Department shall promptly notify the operator and any person who provided comments, of its process decision.

Source: Rule 690-052-0040 — Process Determination, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=690-052-0040.

Last Updated

Jun. 8, 2021

Rule 690-052-0040’s source at or​.us