OAR 690-380-2250
Transfer of Supplemental Water Right or Permit
(1)
When an application for change of the use or place of use for a primary water right is submitted in accordance with OAR 690-380-3000 (Application for Transfer), the applicant also shall indicate whether the land described in the application has an appurtenant supplemental water right or permit. If the applicant intends to transfer the supplemental water right or permit with the primary water right, the applicant shall include information on the supplemental right or permit as part of the transfer application for the primary water right as required under OAR 690-380-3000 (Application for Transfer).(2)
If the applicant does not include the supplemental water right or permit in the transfer application, the Department shall notify the applicant and the land owner, as identified under OAR 690-380-3000 (Application for Transfer)(13), that the supplemental water right will be canceled before the Department issues the order approving the transfer of the primary water right, unless within 30 days after the date of Department notification, the applicant modifies the application to include the supplemental water right or permit or withdraws the application.(3)
The Department may approve the transfer of a supplemental water right or permit in accordance with ORS 540.520 (Application for change of use, place of use or point of diversion) and 540.530 (Order authorizing change of use, place of use or point of diversion). The Department shall not approve the transfer of a supplemental water right or permit if the transfer would result in injury or enlargement.(4)
If the Department approves the transfer of the primary water right but does not approve the transfer of the supplemental water right or permit, the Department shall notify the applicant and the land owner, as identified under OAR 690-380-3000 (Application for Transfer)(13), of the Department’s intent to cancel that portion of the supplemental water right or permit described in the transfer application before the Department issues the primary water right transfer order, unless the applicant withdraws the transfer application within 90 days.(5)
The order issued by the Department approving the transfer of a primary water right shall also cancel any appurtenant supplemental water right or permit not included in the transfer if the applicant does not modify or withdraw the application pursuant to section (2) of this rule or withdraw the application pursuant to section (4) of this rule.
Source:
Rule 690-380-2250 — Transfer of Supplemental Water Right or Permit, https://secure.sos.state.or.us/oard/view.action?ruleNumber=690-380-2250
.