OAR 731-007-0400
Design/Build


(1)

General. The Design/Build form of contracting, as defined in OAR 731-007-0350 (Definitions)(2), has technical complexities that are not readily apparent. ODOT shall only utilize this contracting method with the assistance of knowledgeable staff or consultants who are experienced in its use. In order to utilize the Design/Build process ODOT must be able to reasonably expect the following types of benefits:

(a)

Obtaining, through a Design/Build team, engineering design, plan preparation, value engineering, construction engineering, construction, quality control, and required documentation as a fully integrated function with a single point of Contractor responsibility;

(b)

Integrating value engineering suggestions into the design phase, as the construction Contractor joins the project team early with design responsibilities under a team approach, with the potential of reducing Contract changes;

(c)

Reducing the risk of design flaws, misunderstandings and conflicts inherent in construction Contractors building from designs in which they have had no opportunity for input, with the potential of reducing Contract claims;

(d)

Shortening project duration as construction activity (early submittals, mobilization, subcontracting and advance Work) commences prior to completion of a final design, or where a design solution is still required (as in complex or phased projects); and

(e)

Obtaining innovative design solutions through the collaboration of the Contractor and design team, which would not otherwise be possible if the Contractor had not yet been selected.

(2)

Authority. Agencies shall utilize the Design/Build form of contracting only in accordance with the requirements of division 7 rules. See particularly OAR 731-007-0360 (Use of Alternative Contracting Methods) on “Use of Alternative Contracting Methods.”

(3)

Selection. Design/Build selection criteria may include those factors set forth in OAR 731-007-0390 (RFP Process)(2).

(4)

Qualification Based Selection (QBS). Inapplicable. Because the value of construction services predominates the Design/Build form of contracting, and ODOT is not issuing a personal service Contract, the QBS process mandated by ORS 279C.110 (Selection procedures for consultants to provide services) for State Agencies is not applicable. See ORS 279C.100 (Definitions for ORS 279C.100 to 279C.125)(5) and 279C.110 (Selection procedures for consultants to provide services)(2)(a).

(5)

Licensing. Where the Design/Build Contractor is not a licensed or registered design professional, the Design/Build process contemplates that state licensing and registration requirements related to architectural and engineering services may be fulfilled by design professionals who are employees, subcontractors, joint venturers or in other lawful business relationships with the Design/Build Contractor. Under this approach, Design/Build Contractors are not required to fulfill design licensing or registration requirements at the time of submitting Proposals, but shall specifically identify the licensed design professionals by individual or firm names.

(6)

Performance Security. ORS 279C.375 (Award and execution of contract)(3)(b) provides that for Design/Build Contracts the surety’s obligation on performance bonds, or the Bidder’s obligation on cashier’s or certified checks accepted in lieu thereof, includes the preparation and completion of design and related professional services specified in the Contract. This additional obligation, beyond performance of construction services, extends only to the provision of professional services and related design revisions, corrective Work and associated costs prior to final completion of the Contract (or for such longer time as may be defined in the Contract). The obligation is not intended to be a substitute for professional liability insurance, and does not include errors and omissions or latent defects coverage.

(7)

Contract Requirements. ODOT shall conform its Design/Build contracting practices to all of the following requirements:

(a)

Design Services. The level or type of design services required must be clearly defined within the Solicitation Documents and Contract, along with a description of the level or type of design services previously performed for the project. The services to be performed shall be clearly designated as either design Specifications or performance standards, and performance measurements must be identified.

(b)

Professional Liability. The Contract shall clearly identify the liability of design professionals with respect to the Design/Build Contractor and ODOT, as well as requirements for professional liability insurance.

(c)

Risk Allocation. The Contract shall clearly identify the extent to which ODOT requires an express indemnification from the Design/Build Contractor for any failure to perform, including professional errors and omissions, design warranties, construction operations and faulty Work claims.

(d)

Warranties. The Contract shall clearly identify any express warranties made to ODOT regarding characteristics or capabilities of the completed project (regardless of whether errors occur as the result of improper design, construction, or both), including any warranty that a design will be produced that meets the stated project performance and budget guidelines.

(e)

Incentives. The Contract shall clearly identify any economic incentives and disincentives, the specific criteria that apply and their relationship to other financial elements of the Contract.

(f)

Honoraria. If allowed by the RFP, honoraria or stipends may be provided for early design submittals from qualified finalists during the solicitation process on the basis that ODOT is benefited from such deliverables.