OAR 860-023-0084
General Provisions and Applicability of Electric Service Reliability Rules


(1)

Unless otherwise noted, OAR 860-023-0081 (Definitions and Terms for Electric Service Reliability) through 860-023-0161 (Major Event Filing by Electric Companies) apply to every electric company, effective beginning January 1, 2012.

(2)

A person may apply for waiver of any provision of the Electric Service Reliability Rules. The Commission may grant a waiver upon showing of good cause.

(3)

An electric company must comply with IEEE 1366 in the collecting and analyzing of interruption data and in the calculation and reporting of reliability indices as required by Electric Service Reliability Rules. If there is a conflict between any provision in IEEE 1366 and the Electric Service Reliability Rules, OAR 860-023-0081 (Definitions and Terms for Electric Service Reliability) through 860-023-0161 (Major Event Filing by Electric Companies) govern.

(4)

An electric company must include both “distribution system” interruptions and “interruptions caused by events outside of the distribution system” as defined in IEEE 1366 in the electric company’s record keeping, calculations, reporting, and filing as required by OAR 860-023-0081 (Definitions and Terms for Electric Service Reliability) through 860-023-0161 (Major Event Filing by Electric Companies), effective beginning January 1, 2012.
[Publications: Publications referenced in this rule are available for review at the agency.]

Source: Rule 860-023-0084 — General Provisions and Applicability of Electric Service Reliability Rules, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-023-0084.