OAR 918-271-0030
Correction of Defects


(1)

Defects in electrical installations noted by the electrical inspector shall be corrected and an inspection request made within 20 calendar days of the date of actual notice of deficiency. For the purpose of this rule, actual notice is given when the inspecting jurisdiction does everything required in OAR 918-271-0020 (Requests for Inspection and Notice of Results).

(2)

If corrections cannot reasonably be made within the specified time in section (1) of this rule, or an interpretation or written appeal has been requested, the permit holder shall contact the inspecting jurisdiction and request an extension of time to a specified date or until deficiency is resolved.

(3)

Requests for inspection and requests for extension may be communicated in any way. However, if challenged, the burden of proof is on the requester to document the request was in fact communicated. Responses may also be communicated in any way, but if challenged, the burden of proof is on the inspecting jurisdiction.

Source: Rule 918-271-0030 — Correction of Defects, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=918-271-0030.

Last Updated

Jun. 8, 2021

Rule 918-271-0030’s source at or​.us