(1)

Phased Projects. There shall be an application fee of $100 for each separate phase of the project. In addition, the plan review fee shall be increased in an amount equal to 10 percent of the building permit fee calculated according to OAR 918-460-0050 (Structural Permit Fees) using the value of the particular phase of the project, not to exceed an additional $1,500 for each phase.

(2)

Deferred Submittals. The fee for processing and reviewing deferred plan submittals shall be an amount equal to 65 percent of the building permit fee calculated according to OAR 918-460-0050 (Structural Permit Fees) using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on total project value.
[Publications: Publications referenced are available from the agency.]

Source: Rule 918-460-0070 — Phased Project and Deferred Submittal Fees, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=918-460-0070.

Last Updated

Jun. 8, 2021

Rule 918-460-0070’s source at or​.us