OAR 918-480-0030
Phased Project and Deferred Submittal Fees


When requested to review and approve plans for phased construction or deferred plan submittals under the Oregon Residential Specialty Code, the following fees in addition to the applicable plan review and permit fees apply:

(1)

Phased Permits. There is an application fee of $50 for each separate phase of the project. In addition, the plan review fee is increased in an amount equal to 10 percent of the building permit fee calculated according to OAR 918-480-0020 (One- and Two-Family Dwelling Permit Fees) using the value of the particular phase of the project, not to exceed an additional $1,500 for each phase.

(2)

Deferred Submittals. The fee for processing and reviewing deferred plan submittals is an amount equal to 65 percent of the building permit fee calculated according to OAR 918-480-0020 (One- and Two-Family Dwelling Permit Fees) using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on total project value.
[Publications: Publications referenced are available from the agency.]

Source: Rule 918-480-0030 — Phased Project and Deferred Submittal Fees, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=918-480-0030.

Last Updated

Jun. 8, 2021

Rule 918-480-0030’s source at or​.us