Completion date of improvement
- notice of completion, abandonment or nonabandonment
- contents of notice
Source:
Section 87.045 — Completion date of improvement; notice of completion, abandonment or nonabandonment; contents of notice, https://www.oregonlegislature.gov/bills_laws/ors/ors087.html
.
Notes of Decisions
Where evidence showed construction project was abandoned, the 60-day time period for filing a lien under ORS 87.035 would start to run 60 days after work ceased. D.E.C. Eng. and Surveying v. G & J Invest., 57 Or App 742, 646 P2d 643 (1982)
If owner or mortgagee elects to post and record notice of completion, date of notice is determinative of completion date within the meaning of ORS 87.035. Star Rentals, Inc. v. Seeberg Construction Co., 66 Or App 822, 677 P2d 708 (1984), Sup Ct review denied
Law Review Citations
41 WLR 95 (2005)