Allowable Project Costs


For purposes of projects funded under this division of rules, the allowable costs of a project include:

(1)

Financing costs, including capitalized interest;

(2)

Direct project management costs;

(3)

Costs of consultant services and expenses;

(4)

Construction costs and expenses;

(5)

Costs of property acquisition, including any easement, or right of way directly related to and necessary for the project;

(6)

Costs incurred by the municipality prior to the award if such costs are allowable under the Authority’s adopted policy for reimbursement of pre-award costs;

(7)

Costs of acquiring off-site property for purposes directly related to the project, such as wetland mitigation; and

(8)

Other costs that the Authority determines to be necessary or useful.