(1)

ODOE shall contract with an owner for projects that comply with OAR 330-069-0085 (Program Procedures). ODOE shall prepare and submit to each IOU a summary report for ECMs approved under such contract.

(2)

When the owner and ODOE have signed a contract, the owner must complete the project no later than the date set by the contract, or its amendment in accordance with OAR 330-069-0060 (Extension of Time for Obligated Measures).

(3)

When ODOE finds that the completed project complies with OAR 330-069-0085 (Program Procedures), ODOE shall request the funding IOU to pay the owner an amount not to exceed that set in 330-069-0025 (Maximum Payment Levels).