OAR 330-069-0080
Project Ranking Formula


(1)

TAS:

(a)

ODOE shall rank TAS applications for a building or occupied building by its potential for ECMs. Rank shall be set by a point system based upon data in the EA;

(b)

ODOE shall approve for funding qualified TAS applications in rank order starting with the highest ranked application.

(2)

ECM:

(a)

ODOE shall rank ECM Project applications by this formula:
Project Payment = Ranking Value
E

(A)

Project Payment = The sum of allowable ECM costs where the allowable cost of each ECM is determined by OAR 330-069-0025 (Maximum Payment Levels)(2)(a);

(B)

E = The sum of electricity savings from all ECMs; savings are equal to the life of each ECM times its estimated yearly kilowatt hour savings.

(b)

Any direct application renewable resource part of a project shall not be ranked or funded;

(c)

ODOE shall approve for funding qualified ECM project applications in rank order starting with the lowest ranked.