OAR 345-015-0310
Request for Expedited Review of Special Criteria Facilities
(1)
Any person who proposes to construct and operate a special criteria facility, as defined in section (2), and who chooses to request expedited review of an application for a site certificate must submit to the Department a request for expedited review as described in section (3) with the fee required by the fee schedule established under ORS 469.441 (Justification of fees charged), payable to the Oregon Department of Energy.(2)
“Special criteria facility” means a facility that meets the criteria stated in ORS 469.373 (Expedited processing for certain natural gas energy facilities)(1).(3)
In the request for expedited review, the applicant must provide documentation that the proposed facility is a special criteria facility, as defined in section (2), and:(a)
A description of the facility and the proposed site;(b)
The applicant’s name and address;(c)
A schedule stating when the applicant expects to submit an application for a site certificate; and(d)
A list of all statutes, rules and ordinances applicable to the facility;(4)
Within 14 days after receiving the request for expedited review, the Department must determine, on a preliminary, non-binding basis, whether the proposed facility qualifies for expedited review under this rule and must notify the applicant. The Department may decide, on a preliminary, non-binding basis, that the proposed location of associated transmission lines or new natural gas pipelines outside of existing rights of way imposes no significant impact. The Department must provide to the applicant a mailing list of persons including, but not limited to, the agencies listed in ORS 469.373 (Expedited processing for certain natural gas energy facilities)(4).(5)
After the Department has made the determination described in section (4), the applicant may submit a preliminary application for a site certificate, as described in OAR 345-021-0000 (General Requirements) and 345-021-0010 (Contents of an Application), subject to the following:(b)
Unless the Department directs otherwise, the applicant must send an electronic copy of the preliminary application to each person on the mailing list described in section (4). The applicant must provide a printed copy of all or part of the preliminary application to any person on the mailing list upon request.(6)
Within 30 days after receiving a preliminary application for a site certificate, the Department must issue a project order. In the project order, the Department may make changes to the analysis areas. The project order is not a final order. The Council or the Department may amend the project order at any time.(7)
Within 30 days after receiving a preliminary application for a site certificate, the Department must either:(a)
Notify the applicant that the application is complete; or(b)
Notify the applicant that the application is not complete and describe the information needed to complete the application, to the extent known to the Department at the time of the notification.(8)
If additional information is needed to complete the application, the applicant must submit the information to the Department. If follow-up requests for additional information are needed, the Department may specify dates by which the applicant must submit the information. The Department may specify the dates by which the applicant must submit additional information needed to complete the application. At the request of the applicant, the Department may extend the deadline for submission of the information. If the applicant does not submit the information by the deadline specified by the Department, including any allowed extension, the Council may reject the application. The rejection of an application is subject to appeal under ORS 469.403 (Rehearing on approval or rejection of application for site certificate or amendment)(3).(9)
An application is complete when the Department finds that the applicant has submitted information adequate for the Council to make findings or impose conditions on all applicable Council standards. The Department may find that the application is complete without requiring the applicant to submit all information described under OAR 345-021-0000 (General Requirements) and 345-021-0010 (Contents of an Application). The Department must notify the applicant when the Department finds that the application is complete and, if needed, may request the application supplement described in OAR 345-021-0055 (Distribution of a Complete Application).(10)
The date of filing is the date the Department receives the application supplement described in OAR 345-021-0055 (Distribution of a Complete Application) or, if no supplement is needed, the date the Department notifies the applicant that the application is complete.(11)
After a determination that an application is complete, the Department may require additional information from the applicant if the Department identifies a need for that information during its review of the application. Submission of such information does not constitute an amendment of the application.(12)
In the notification to the applicant that the application is complete, as described in section (7)(a) or (9), the Department must instruct the applicant send a copy of the notice described in section (13) and a copy of the application supplement, if any, to specified persons including but not limited to the agencies listed in ORS 469.373 (Expedited processing for certain natural gas energy facilities)(4).(13)
The Department must prepare a notice that:(a)
States that the application is complete and specifies the date of filing;(b)
Requests the agency reports as described in OAR 345-015-0200 (Notice to Agencies that the Application is Complete); and(c)
Includes the statements required by ORS 469.373 (Expedited processing for certain natural gas energy facilities)(4)(a) and (b).(14)
At the time specified in section (15), the Department must issue a public notice, including but not limited to:(a)
A description of the proposed facility and the general location of the energy facility;(b)
The date, time, and location of a public informational meeting on the application;(c)
A statement that the application has been filed;(d)
Addresses of locations where the public may review copies of the application; and(e)
The name, address, email address, and telephone number of the Department’s representative to contact for more information.(15)
At least 14 days before the meeting described in section (16), the Department must:(a)
Submit the notice described in section (14) for publication in a newspaper of general circulation available in the vicinity of the proposed facility; and(b)
Send the notice described in section (14) by mail or email to all persons on:(A)
The Council’s general mailing list as defined in OAR 345-011-0020 (Agendas for Regular Meetings);(B)
Any special mailing list set up for the proposed project; and(C)
The list of property owners provided in Exhibit F of the application.(16)
The Department must hold a public informational meeting on the application.(17)
Within 90 days after the date of filing, the Department must issue a draft proposed order including, but not limited to:(a)
A description of the proposed facility;(b)
A list of the permits, licenses and certificates that are addressed in the application and that are required for the construction or operation of the proposed facility;(c)
A list of the statutes, rules and local ordinances that are the standards and criteria for approval of any permit, license or certificate addressed in the application and that are required for the construction or operation of the proposed facility; and(d)
Proposed findings regarding compliance with the applicable standards and criteria for approval of a site certificate and specifying conditions that are required for the facility to comply.(18)
The Council must review the draft proposed order. In accordance with ORS 469.370 (Draft proposed order for hearing)(3), when the Council meets to review a draft proposed order, the Council may not permit the applicant, reviewing agencies, or the public to comment on any issue that may be the basis for a contested case.(19)
After the Council’s review as described in section (18), the Department must issue a proposed order.(20)
At the time specified in section (21), the Department must issue a public notice, including but not limited to:(a)
A description of the facility and its general location;(b)
The name, address, email address, and telephone number of the Department’s representative to contact for more information;(c)
A statement that the Department has issued a proposed order and that copies of the application and proposed order are available for inspection at no cost and will be provided at reasonable cost;(d)
The date, time and location of a public hearing on the proposed order;(e)
A statement that the record for public comment on the application will close at the conclusion of the hearing and that failure to raise an issue in person or in writing prior to the close of the record with sufficient specificity to afford the decision maker an opportunity to respond to the issue precludes consideration of the issue in a contested case or by a court on judicial review of the Council’s decision;(f)
A statement that to raise an issue with sufficient specificity, a person must present facts that support the person’s position on the issue; and(g)
A statement that the hearing is the only opportunity for the public to make a factual record for review and that persons having objection to the proposed order must appear at the hearing in person or in writing and present factual evidence, including any expert testimony, and legal argument.(21)
At least 20 days before the hearing described in section (22), the Department must:(a)
Submit the notice described in section (20) for publication in a newspaper of general circulation available in the vicinity of the proposed facility; and(b)
Send the notice described in section (20) by mail or email to all persons on:(A)
The Council’s general mailing list as defined in OAR 345-011-0020 (Agendas for Regular Meetings); and(B)
Any special mailing list set up for the proposed project; and(C)
The list of property owners provided in Exhibit F of the application.(22)
The Council must hold at least one public hearing on the proposed order in the area affected by the proposed facility according to the procedures described in OAR 345-015-0320 (Public Hearing Procedures for Special Criteria Facilities).(23)
Before the conclusion of the hearing described in section (22), the applicant may either:(a)
Request an opportunity to present additional written evidence, arguments or testimony regarding the application; or(b)
Request a contested case hearing on the application. Not later than 7 days after making a request in the public hearing, the applicant must submit the request to the Council in writing, including evidence sufficient to show good cause for the contested case hearing.(24)
Except as described in section (27), following the close of the record of the public hearing, the Department must issue a draft final order for the Council. In preparing the draft final order, the Department must take into account the entire record, including the summary prepared by the hearing officer described in OAR 345-015-0320 (Public Hearing Procedures for Special Criteria Facilities).(25)
Except as described in section (27), within six months after the date of filing, the Council must make its decision on the record and the draft final order. The Council must:(a)
Grant the site certificate;(b)
Grant the site certificate with conditions;(c)
Deny the site certificate; or(d)
Determine that the proposed facility is not a special criteria facility as defined in section (2) and is not eligible for expedited review under this rule.(26)
The Council must issue a site certificate for the proposed facility if the Council determines that the proposed facility, with any required conditions to the site certificate, will comply with:(a)
The requirements for expedited review as specified in this rule;(b)
The standards adopted by the Council pursuant to ORS 469.501 (Energy facility siting, construction, operation and retirement standards)(1)(a), (c) to (e), (g), (h) and (L) to (o);(c)
The requirements of ORS 469.503 (Requirements for approval of energy facility site certificate)(3); and(d)
The requirements of ORS 469.504 (Facility compliance with statewide planning goals)(1)(b).(27)
If the applicant requests a contested case hearing as described in section (23)(b), the Council, after considering the request in a public meeting, may grant the request if the Council finds that the applicant has shown good cause for a contested case hearing.(28)
If the Council grants the request for a contested case hearing, the Department must issue a notice of a contested case on the proposed order as described in OAR 345-015-0014 (Contested Case Notices). The Council must then consider the application under the same contested case procedures used for a nonexpedited application for a site certificate.(29)
If, as described in section (25), the Council determines that the proposed facility is not a special criteria facility and is not eligible for expedited review under this rule, then the Council must consider the application under the same review procedures used for a nonexpedited application from the point of the applicant’s submission of an application. The Department must treat the application before the Council at the time of the determination as a preliminary application for the purpose of review under OAR 345-015-0190 (Determination of Completeness), except that within 30 days after the Council’s determination, the Department must determine whether the application is complete. The Department must notify the applicant as described in OAR 345-015-0190 (Determination of Completeness)(1) and the Department must issue an amended project order that includes the Council standards that were not applicable under expedited review. For the purpose of the land use standard, the applicant must obtain a Council determination as described under OAR 345-022-0030 (Land Use)(2)(b), and the Council must apply the applicable substantive criteria in effect on the date the application was originally submitted under section (5).(30)
The applicant may withdraw its request for expedited review under this rule at any time and request that the Council consider its application under the same review procedures used for a nonexpedited application. After such a request, the Department must treat the application as a preliminary application for the purpose of review under OAR 345-015-0190 (Determination of Completeness) as described in section (29). For the purpose of the land use standard, the applicant must obtain a Council determination as described under OAR 345-022-0030 (Land Use)(2)(b), and the Council must apply the applicable substantive criteria in effect on the date the application was originally submitted under section (5).
Source:
Rule 345-015-0310 — Request for Expedited Review of Special Criteria Facilities, https://secure.sos.state.or.us/oard/view.action?ruleNumber=345-015-0310
.