OAR 437-003-0752
Site-Specific Erection Plan
(1)
The site-specific erection plan must:(a)
Be developed by a qualified person;(b)
Identify the site;(c)
Be available at the work site; and(d)
Be signed by the qualified person responsible for its development and any modification(s).(2)
The site-specific erection plan must contain the following:(a)
A description of the procedures that will be used to comply with 1926.754(a). Consider the dead weight of the structure, the weight and working reactions of all static and dynamic loads placed on it, and all external forces that may be applied such as wind and reactions by erection equipment.(b)
A description of the procedures and work practices that will be used to protect employees from falls and other hazards where it is necessary to walk/work on suspended loads. Employee(s) are allowed on suspended loads only when a competent person has determined that it is the safest way to accomplish a specific task or there is no other way to do the work.
Source:
Rule 437-003-0752 — Site-Specific Erection Plan, https://secure.sos.state.or.us/oard/view.action?ruleNumber=437-003-0752
.