OAR 660-012-0050
Transportation Project Development


(1)

For projects identified by ODOT pursuant to OAR chapter 731, division 15, project development shall occur in the manner set forth in that division.

(2)

Regional TSPs shall provide for coordinated project development among affected local governments. The process shall include:

(a)

Designation of a lead agency to prepare and coordinate project development;

(b)

A process for citizen involvement, including public notice and hearing, if project development involves land use decision-making. The process shall include notice to affected transportation facility and service providers, MPOs, and ODOT;

(c)

A process for developing and adopting findings of compliance with applicable statewide planning goals, if any. This shall include a process to allow amendments to acknowledged comprehensive plans where such amendments are necessary to accommodate the project; and

(d)

A process for developing and adopting findings of compliance with applicable acknowledged comprehensive plan policies and land use regulations of individual local governments, if any. This shall include a process to allow amendments to acknowledged comprehensive plans or land use regulations where such amendments are necessary to accommodate the project.

(3)

Project development addresses how a transportation facility or improvement authorized in a TSP is designed and constructed. This may or may not require land use decision-making. The focus of project development is project implementation, e.g. alignment, preliminary design and mitigation of impacts. During project development, projects authorized in an acknowledged TSP shall not be subject to further justification with regard to their need, mode, function, or general location. For purposes of this section, a project is authorized in a TSP where the TSP makes decisions about transportation need, mode, function and general location for the facility or improvement as required by this division.

(a)

Project development does not involve land use decision-making to the extent that it involves transportation facilities, services or improvements identified in OAR 660-012-0045 (Implementation of the Transportation System Plan)(1)(a); the application of uniform road improvement design standards and other uniformly accepted engineering design standards and practices that are applied during project implementation; procedures and standards for right-of-way acquisition as set forth in the Oregon Revised Statutes; or the application of local, state or federal rules and regulations that are not a part of the local government’s land use regulations.

(b)

Project development involves land use decision-making to the extent that issues of compliance with applicable requirements requiring interpretation or the exercise of policy or legal discretion or judgment remain outstanding at the project development phase. These requirements may include, but are not limited to, regulations protecting or regulating development within floodways and other hazard areas, identified Goal 5 resource areas, estuarine and coastal shoreland areas, and the Willamette River Greenway, and local regulations establishing land use standards or processes for selecting specific alignments. They also may include transportation improvements required to comply with ORS 215.296 (Standards for approval of certain uses in exclusive farm use zones) or 660-012-0065 (Transportation Improvements on Rural Lands)(5). When project development involves land use decision-making, all unresolved issues of compliance with applicable acknowledged comprehensive plan policies and land use regulations shall be addressed and findings of compliance adopted prior to project approval.

(c)

To the extent compliance with local requirements has already been determined during transportation system planning, including adoption of a refinement plan, affected local governments may rely on and reference the earlier findings of compliance with applicable standards.

(4)

Except as provided in section (1) of this rule, where an Environmental Impact Statement (EIS) is prepared pursuant to the National Environmental Policy Act of 1969, project development shall be coordinated with the preparation of the EIS. All unresolved issues of compliance with applicable acknowledged comprehensive plan policies and land use regulations shall be addressed and findings of compliance adopted prior to issuance of the Final EIS.

(5)

If a local government decides not to build a project authorized by the TSP, it must evaluate whether the needs that the project would serve could otherwise be satisfied in a manner consistent with the TSP. If identified needs cannot be met consistent with the TSP, the local government shall initiate a plan amendment to change the TSP or the comprehensive plan to assure that there is an adequate transportation system to meet transportation needs.

(6)

Transportation project development may be done concurrently with preparation of the TSP or a refinement plan

Source: Rule 660-012-0050 — Transportation Project Development, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=660-012-0050.

Last Updated

Jun. 8, 2021

Rule 660-012-0050’s source at or​.us