OAR 732-005-0071
Protest Procedure


The Division will conduct a process to resolve protests of funding decisions made by the Oregon Department of Transportation.

(1)

Within 30 days of notification of a funding decision, the STF Agency may file a protest of the decision.

(a)

The STF Agency will address the protest to the Administrator of the Division; and

(b)

The protest will identify the project or proposed project affected by the funding decision, the Recipient or proposed Recipient affected by the decision, any arguments pertaining to the protest, and the requested remedy.

(2)

The Division will investigate the protest and will make a written statement of finding within 30 days.

(3)

Within 10 working days of receipt of the statement of finding, the STF Agency may request a review of the statement of finding. After a review of the statement of finding, the Administrator of the Division will issue a final decision.
Last Updated

Jun. 8, 2021

Rule 732-005-0071’s source at or​.us