(1)

The Project Manager of a pre-certified project must submit an application for project certification to the Program Administrator.

(2)

The Commission will certify a project that demonstrates:

(a)

Ownership of, or subscription to, at least 50 percent of the project nameplate capacity;

(b)

Ownership or subscription by at least five different participants;

(c)

Compliance with applicable low-income capacity requirements;

(d)

Commission approval of modification to pre-certified project as required in OAR 860 088-0040(6), if applicable; and

(e)

Satisfaction of any other condition identified by the Commission at the time of pre certification.

(3)

The Program Administrator reviews applications for certification in the order received for compliance with applicable requirements and presents applications to the Commission for certification. The Program Administrator must notify the Project Manager of any deficiencies and allow reasonable time for remedy.

Source: Rule 860-088-0050 — Project Certification, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=860-088-0050.