OAR 340-150-0360
Requirements for Internally Lined USTs


(1)

Internally lined USTs without corrosion protection. An owner and permittee of an internally lined UST that does not have corrosion protection must have the UST internally inspected or assessed in accordance with a method that has been evaluated and approved by a third party to ensure the tank is structurally sound and the lining is still performing in accordance with all original design specifications. An owner and permittee must have the internal lining inspections or assessments conducted:

(a)

Within ten years after lining; and

(b)

Every five years thereafter.

(2)

Internally lined USTs with corrosion protection. An owner and permittee of an internally lined UST that has corrosion protection must conduct internal lining inspections or assessments of the UST as required by section (1) of this rule. However, internal inspections are not required if the owner and permittee meet each of the following conditions:

(a)

The integrity of the UST was inspected or assessed before the addition of corrosion protection;

(b)

Written documentation of the inspection results and the internal inspection or assessment is provided to the department that demonstrates the work was conducted in accordance with a code of practice developed by a nationally recognized association, an independent testing laboratory or by a method that has been third party evaluated and approved: and

(c)

If the original integrity inspection or assessment was not conducted, documentation is not available or the documentation is not sufficient as determined by the department, an owner and permittee must complete at least one internal inspection of the tank lining using the method specified by American Petroleum Institute Publication 1631, “Recommended Practice for the Interior Lining of Existing Steel Underground Storage Tanks”.

(3)

The owner and permittee must permanently decommission an UST system if any internal inspection determines that the UST is no longer structurally sound.
[Publications: Publications referenced are available from the agency.]

Source: Rule 340-150-0360 — Requirements for Internally Lined USTs, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-150-0360.

340‑150‑0001
Purpose and Scope
340‑150‑0006
Applicability and General Requirements
340‑150‑0008
Exemptions and Deferrals
340‑150‑0010
Definitions
340‑150‑0020
UST General Permit Registration Certificate Required
340‑150‑0021
Termination of Temporary Permits
340‑150‑0052
Modification of Registration Certificates For Changes in Ownership and Permittee
340‑150‑0080
Denial, Suspension or Revocation of General Permit Registration Certificates
340‑150‑0102
Termination of General Permit Registration Certificates for Installation, Operation and Temporary Closure
340‑150‑0110
UST General Permit Registration, Annual Compliance and Other Fees
340‑150‑0135
General Requirements for Owners and Permittees
340‑150‑0137
UST Systems with Field-Constructed Tanks and Airport Hydrant Fuel Distribution Systems
340‑150‑0140
Requirements for Sellers of USTs
340‑150‑0150
Depositing Regulated Substances in USTs
340‑150‑0152
Requirements for Distributors of Regulated Substances for Deposit into USTs
340‑150‑0156
Performance of UST Services by Owners or Permittees
340‑150‑0160
General Permit Requirements for Installing an UST System
340‑150‑0163
General Permit Requirements for Operating an UST System
340‑150‑0167
General Permit Requirements for Temporary Closure of an UST System
340‑150‑0168
General Permit Requirements for Decommissioning an UST System by Permanent Closure or Change-in-Service
340‑150‑0180
Site Assessment Requirements
340‑150‑0200
Training Requirements for UST System Operators and Emergency Response Information
340‑150‑0210
Training Requirements for UST Operators
340‑150‑0250
Expedited Enforcement Process
340‑150‑0302
Installation of Used USTs
340‑150‑0310
Spill and Overfill Prevention Equipment and Testing Requirements
340‑150‑0315
Periodic operation and maintenance walkthrough inspections
340‑150‑0320
Corrosion Protection Performance Standards for USTs and Piping
340‑150‑0325
Operation and Maintenance of Corrosion Protection
340‑150‑0350
UST System Repairs
340‑150‑0352
UST System Modifications and Additions
340‑150‑0354
UST System Replacements
340‑150‑0360
Requirements for Internally Lined USTs
340‑150‑0400
General Release Detection Requirements for Petroleum UST Systems
340‑150‑0410
Release Detection Requirements and Methods for Underground Piping
340‑150‑0420
Release Detection Requirements for Hazardous Substance UST Systems
340‑150‑0430
Inventory Control Method of Release Detection
340‑150‑0435
Statistical Inventory Reconciliation Method of Release Detection
340‑150‑0440
Manual Tank Gauging Release Detection Method
340‑150‑0445
Tank Tightness Testing for Release Detection and Investigation
340‑150‑0450
Automatic Tank Gauging Release Detection Method
340‑150‑0465
Interstitial Monitoring Release Detection Method
340‑150‑0470
Other Methods of Release Detection
340‑150‑0500
Reporting Suspected Releases
340‑150‑0510
Suspected Release Investigation and Confirmation Steps
340‑150‑0520
Investigation Due to Off Site Impacts
340‑150‑0540
Applicability to Previously Closed UST Systems
340‑150‑0550
Definitions for OAR 340-150-0555 and 340-150-0560
340‑150‑0555
Compliance Dates for USTs and Piping
340‑150‑0560
Upgrading Requirements for Existing UST Systems
340‑150‑0600
Delegation of Program Administration
340‑150‑0620
Approval of More Stringent Performance Standards
Last Updated

Jun. 8, 2021

Rule 340-150-0360’s source at or​.us