(1)

Verification services provided and completed must meet the requirements of OAR 340-272-0405 (Notice of Verification Services) through OAR 340-272-0495 (Independent Review and Completion of Verification Services), as applicable to the type of CFP report or fuel pathway application submitted under OAR chapter 340, division 253 or emissions data report submitted under OAR chapter 340, division 215.

(2)

Requirements for responsible entities.

(a)

Responsible entities must engage the services of a verification body that meets the requirements and criteria under OAR 340-272-0210 (Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers) and has been approved by DEQ under OAR 340-272-0220 (DEQ Review and Approval of Verification Bodies and Verifiers) to perform verification under this division for the type of verification services applicable to the responsible entity.

(b)

A responsible entity that has been notifed by DEQ or by it’s verification body that the verification body’s DEQ approval has been suspended or revoked, must engage the services of a different DEQ-approved verification body to perform verification.

(c)

Each responsible entity must ensure that the verification services provided on its behalf meet the requirements of this division.

(d)

Records retention and availability requirements.

(A)

Responsible entities must retain records necessary for completing verification services and records requested by the verification team according to the recordkeeping requirements of OAR chapter 340, division 215 or OAR chapter 340, division 253, as applicable.

(B)

Responsible entities must retain for verification purposes and make available to the verification team the following:
(i)
All information and documentation used to calculate and report emissions, fuel quantities, and fuels and electricity transactions;
(ii)
All data and information required by or submitted under OAR chapter 340, division 215 or OAR chapter 340, division 253; and
(iii)
Other data and information as necessary in order for verification services to be completed.

(C)

Responsible entities must maintain documentation to support any revisions made to the initial report or fuel pathway application submitted to DEQ as a result of verification. Documentation for all submittals must be retained by the responsible entity in paper or electronic format for a period of at least seven years.

(3)

Requirements for verification bodies and verifiers.

(a)

Eligibility to perform verification.

(A)

A verification body or verifier must meet the requirements and criteria of OAR 340-272-0210 (Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers) and must have DEQ approval under OAR 340-272-0220 (DEQ Review and Approval of Verification Bodies and Verifiers) to be eligible to perform verification under this division.

(B)

Verifiers must be employed by, or contracted with a DEQ-approved verification body in order to provide verification services under this division.

(b)

Subcontracting.

(A)

Any verification body that elects to subcontract a portion of verification services must meet the following requirements:
(i)
The verification body must assume full responsibility for verification services provided by subcontractor verifiers;
(ii)
A verification body may not use subcontractors to meet the minimum lead verifier requirements as specified under OAR 340-272-0210 (Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers)(3)(a); and
(iii)
A verification body may not use a subcontractor as the independent reviewer.

(B)

All subcontractors must apply for and meet the requirements and criteria for DEQ approval under OAR 340-272-0210 (Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers) and be approved by DEQ under OAR 340-272-0220 (DEQ Review and Approval of Verification Bodies and Verifiers) in order to provide the verification services for which the subcontractor has been engaged by the verification body.

(c)

If a verification body receives a final determination frin DEQ under OAR 340-272-0220 (DEQ Review and Approval of Verification Bodies and Verifiers)(3) that is described in paragraphs (A) through (C) below,, then the verification body must provide written notification all responsible entities with which it is currently engaged to provide verification services or that have received verification services from it within the past six months of DEQ’s final determination within ten days of receiving such final determination, and the verification body may not continue to provide verification services until the verification body receives DEQ approval to recommence such services under OAR 340-272-0220 (DEQ Review and Approval of Verification Bodies and Verifiers):

(A)

Any modification relevant to the verification services provided;

(B)

Suspension of DEQ approval of the verification body or any of its verifiers, lead verifiers, sector specific verifiers, or subcontractors; or

(C)

Revocation of DEQ approval of the verification body or any of its verifiers, lead verifiers, sector specific verifiers, or subcontractors.

(d)

Records retention.

(A)

Verification bodies that provide verification services under this division must retain documentation relating to verification in paper or electronic format for a period of at least seven years following the submission of each verification statement.

(B)

The documentation must allow for a transparent review of how a verification body reached its conclusion in the verification statement, including independent review. At a minimum, the documentation retained must include:
(i)
Report(s) or fuel pathway application(s) submitted by the responsible entity to DEQ for which verification services are being provided;
(ii)
Contracts for verification;
(iii)
Verification plan(s);
(iv)
Sampling plan(s);
(v)
Verification report(s);
(vi)
Verification statement(s); and
(vii)
Any other documentation, calculations, and verification notes developed as part of providing and completing verification services.

Source: Rule 340-272-0300 — Requirements for Verification Services, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-272-0300.

340‑272‑0010
Purpose and Scope
340‑272‑0020
Definitions
340‑272‑0100
General Requirements for Verification of Reports and Fuel Pathway Applications
340‑272‑0110
Requirements for Verification of CFP Reports and Fuel Pathway Applications Submitted under OAR Chapter 340, Division 253
340‑272‑0120
Requirements for Verification of GHG Reporting Program Emissions Data Reports Submitted under OAR Chapter 340, Division 215
340‑272‑0210
Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers
340‑272‑0220
DEQ Review and Approval of Verification Bodies and Verifiers
340‑272‑0300
Requirements for Verification Services
340‑272‑0350
DEQ Review and Approval of Verification and Re-verification Requirements
340‑272‑0355
DEQ Data Requests and Audits
340‑272‑0405
Notice of Verification Services
340‑272‑0410
Scoping Verification Services
340‑272‑0415
Verification Plan
340‑272‑0420
Site Visits
340‑272‑0425
Sampling Plan
340‑272‑0430
Data Checks
340‑272‑0435
Documentation of Differences and Modifications to Reports and Fuel Pathway Applications
340‑272‑0440
Findings
340‑272‑0445
Log of Issues
340‑272‑0450
Material Misstatement Assessments for CFP Fuel Pathways and Quarterly Fuel Transactions Submitted under OAR Chapter 340, Division 253
340‑272‑0455
Material Misstatement Assessments for CFP Project Reports Submitted under OAR Chapter 340, Division 253
340‑272‑0460
Material Misstatement Assessments for Emissions Data Submitted under OAR Chapter 340, Division 215
340‑272‑0465
Review of Missing Data Substitution
340‑272‑0470
Review of Operations and Emissions for Emissions Data Reports Submitted under OAR Chapter 340, Division 215
340‑272‑0495
Independent Review and Completion of Verification Services
340‑272‑0500
Requirements for Conflict of Interest Evaluation
Last Updated

Jun. 8, 2021

Rule 340-272-0300’s source at or​.us