OAR 340-272-0405
Notice of Verification Services


(1)

Before a verification body commences any verification services for the responsible entity, the responsible entity must ensure the verification body submits a notice of verification services to DEQ that meets the requirements of this rule. The notice of verification services must be submitted after DEQ has provided a determination that the potential for a conflict of interest is acceptable as specified under OAR 340-272-0500 (Requirements for Conflict of Interest Evaluation)(7) and that verification services may proceed.

(a)

If the conflict of interest evaluation submitted by the responsible entity and the notice of verification services submitted by the verification body are submitted at the same time, verification services may not begin until DEQ has determined the potential for conflict of interest is acceptable in writing.

(b)

Except as provided in subsection (a), the verification body may begin verification services for the responsible entity after the notice of verification services is received by DEQ, but must allow a minimum of 14 calendar days advance notice of a site visit unless an earlier date is approved by DEQ.

(2)

The verification notice must include the following information:

(a)

A list of the staff designated to provide verification services as a verification team, including the names of each individual, the lead verifier, and all subcontractors, and a description of the roles and responsibilities each member will have during verification. The independent reviewer must also be listed separately;

(b)

Documentation that the verification team has the skills required to provide verification services for the responsible entity and type of report or fuel pathway application requiring verification. When required by DEQ, the notice must include a demonstration that the verification team includes at least one individual approved by DEQ as a sector specific verifier that is not also the independent reviewer, but may be the lead verifier; and

(c)

General information about the responsible entity, including the following, as applicable:

(A)

Name and list of facilities and other locations that will be subject to verification, and contact, address, telephone number, and e-mail address for each facility;

(B)

The industry sector, North American Industry Classification System (NAICS) code, or source identification number for reporting facilities under OAR chapter 340, division 215.;

(C)

The CFP ID(s) for the responsible entity under OAR chapter 340, division 253.;

(D)

The date(s) of the site visit if full verification is being provided and if required under OAR 340-272-0420 (Site Visits), with physical address and contact information.; and

(E)

A brief description of expected verification services to be provided, including expected completion date and whether quarterly review is planned in the context of an annual verification requirement.

(3)

The responsible entity must ensure the verification body submits an updated notice of verification services to DEQ immediately if any of the information under section (2) changes after the notice of verification services is submitted to DEQ. When an updated notice of verification services is submitted to DEQ, the conflict of interest must be reevaluated and information must be resubmitted according to OAR 240-272-0500. Verification services must be suspended until DEQ approves the resubmitted conflict of interest evaluation information in writing.

Source: Rule 340-272-0405 — Notice of Verification Services, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=340-272-0405.

340‑272‑0010
Purpose and Scope
340‑272‑0020
Definitions
340‑272‑0100
General Requirements for Verification of Reports and Fuel Pathway Applications
340‑272‑0110
Requirements for Verification of CFP Reports and Fuel Pathway Applications Submitted under OAR Chapter 340, Division 253
340‑272‑0120
Requirements for Verification of GHG Reporting Program Emissions Data Reports Submitted under OAR Chapter 340, Division 215
340‑272‑0210
Applications and Criteria for DEQ Approval of Verification Bodies and Verifiers
340‑272‑0220
DEQ Review and Approval of Verification Bodies and Verifiers
340‑272‑0300
Requirements for Verification Services
340‑272‑0350
DEQ Review and Approval of Verification and Re-verification Requirements
340‑272‑0355
DEQ Data Requests and Audits
340‑272‑0405
Notice of Verification Services
340‑272‑0410
Scoping Verification Services
340‑272‑0415
Verification Plan
340‑272‑0420
Site Visits
340‑272‑0425
Sampling Plan
340‑272‑0430
Data Checks
340‑272‑0435
Documentation of Differences and Modifications to Reports and Fuel Pathway Applications
340‑272‑0440
Findings
340‑272‑0445
Log of Issues
340‑272‑0450
Material Misstatement Assessments for CFP Fuel Pathways and Quarterly Fuel Transactions Submitted under OAR Chapter 340, Division 253
340‑272‑0455
Material Misstatement Assessments for CFP Project Reports Submitted under OAR Chapter 340, Division 253
340‑272‑0460
Material Misstatement Assessments for Emissions Data Submitted under OAR Chapter 340, Division 215
340‑272‑0465
Review of Missing Data Substitution
340‑272‑0470
Review of Operations and Emissions for Emissions Data Reports Submitted under OAR Chapter 340, Division 215
340‑272‑0495
Independent Review and Completion of Verification Services
340‑272‑0500
Requirements for Conflict of Interest Evaluation
Last Updated

Jun. 8, 2021

Rule 340-272-0405’s source at or​.us