OAR 350-081-0044
Expiration of Approvals
(1)
Notice Not Required: Expiration of any land use approval issued pursuant to this Management Plan shall be automatic. Failure to give notice of expiration shall not affect the expiration of a land use approval.(2)
Land Use Approvals without Structures: Any land use approval issued pursuant to this Management Plan for a use or development that does not include a structure shall expire two years after the date the land use approval was granted, unless the use or development was established according to all specifications and conditions of approval in the land use approval. For land divisions, “established” means the final deed or plat has been recorded with the county recorder or auditor.(3)
Land Use Approvals with Structures: Any land use approval issued pursuant to this Management Plan for a use or development that includes a structure shall expire as follows:(a)
When construction has not commenced within two years of the date the land use approval was granted; or(b)
When the structure has not been completed within two years of the date of commencement of construction.(4)
Commencement of Construction: As used in subsection (3)(a) above, commencement of construction shall mean actual construction of the foundation or frame of the approved structure. For utilities and developments without a frame or foundation, commencement of construction shall mean actual construction of support structures for an approved above ground utility or development or actual excavation of trenches for an approved underground utility or development. For roads, commencement of construction shall mean actual grading of the roadway.(5)
Completion of Structure: As used in subsection (3)(b) above, completion of the structure shall mean (1) completion of the exterior surface(s) of the structure and (2) compliance with all conditions of approval in the land use approval.(6)
Extension of Validity of Land Use Approvals: A request for extension of the time frames in subsections (2), (3)(a) or (3)(b), above, shall be submitted in writing before the applicable expiration date.(a)
A reviewing agency may grant one 12-month extension to the validity of a land use approval if it determines that events beyond the control of the applicant prevented commencement of the use or development (applicable to section (2) above) or commencement of construction (applicable to subsection (3)(a) above) within the original two-year time frame.(b)
An agency may also grant one 12-month extension if it determines that events beyond the control of the applicant prevented completion of the structure (applicable to subsection (3)(b) above) within the original two-year time frame.(c)
A request for extension shall state the reason why events beyond the control of the applicant warrant an extension.(d)
Approval or denial of a request for extension shall be considered an administrative decision.(7)
Vested Rights: The laws of the states of Oregon and Washington concerning vested rights shall not apply in the National Scenic Area. A person has a vested right for as long as the land use approval does not expire.
Source:
Rule 350-081-0044 — Expiration of Approvals, https://secure.sos.state.or.us/oard/view.action?ruleNumber=350-081-0044
.