OAR 690-020-0065
Plan Requirements for New Dams or to Increase Dam Height: Construction Administration


The Engineer of Record shall submit plans for administering the construction of the Dam to the State Engineer for approval. Construction plans must include the following:

(1)

A provision stating that the Engineer of Record or an employee working for the Engineer of Record shall be on-site as needed for instructions to the contractor, approval of initial excavation, acceptance of materials, and general project administration;

(2)

A provision stating that the Dam owner shall cease construction activity if the Engineer of Record is no longer retained or for any reason cannot complete necessary construction administration activities. Construction may resume when a new Engineer of Record is employed, the State Engineer has been notified of the new Engineer of Record, and both Engineers have discussed the project;

(3)

A provision stating that the Engineer of Record will observe the Dam during construction as needed to determine if construction is consistent with approved design and construction documents. This provision shall also include a description of how the Engineer of Record will determine if construction work in progress fails to conform to the approved plans and specifications, and that such nonconforming work will be corrected;

(4)

A provision stating that the Engineer of Record shall confirm Foundation design assumptions once surface materials have been stripped and the Cutoff Trench excavated. Changes in actual Foundation conditions from assumptions made in the initial site evaluation shall be communicated to the State Engineer;

(5)

A provision in which the Engineer of Record shall maintain a record of construction that shall include:

(a)

Logs of construction inspections whenever such inspections are made by the Engineer of Record or the Engineer of Record’s employee;

(b)

All test results pertaining to construction;

(c)

Photographs; and

(d)

Construction problems and remedies.

(6)

A provision stating that the Engineer of Record shall complete and stamp As-built Drawings and a final construction report, including statements that the observations are either consistent or inconsistent with the design drawings and specifications. If key elements of construction were not observed, the construction report shall detail those specific elements that were not observed.

Source: Rule 690-020-0065 — Plan Requirements for New Dams or to Increase Dam Height: Construction Administration, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=690-020-0065.

690‑020‑0000
Purpose and Applicability
690‑020‑0022
Definitions
690‑020‑0024
General Department Authorities and Intergovernmental Coordination
690‑020‑0026
Fees
690‑020‑0028
Preliminary Plans and Specifications for Construction of New Dams or to Increase Dam Height
690‑020‑0035
Minimum Engineering Requirements for Final Design of New Dams or to Increase Dam Height
690‑020‑0036
Design Requirements for New Dams or to Increase Dam Height: Site Suitability and Geotechnical Evaluation
690‑020‑0037
Design Requirements for New Dams or to Increase Dam Height: Hydrology and Inflow Design Flood
690‑020‑0038
Design Requirements for New Dams or to Increase Dam Height: Embankment Dam Structures
690‑020‑0041
Design Requirements for New Dams or to Increase Dam Height: Concrete Dam Structures
690‑020‑0042
Minimum Design Requirements for New Dams or to Increase Dam Height: Spillways
690‑020‑0043
Design Requirements for New Dams or to Increase Dam Height: Penetrating Conduit(s) and Control of Flow through Conduits
690‑020‑0044
Design Requirements for New Dams or to Increase Dam Height: Instrumentation for Monitoring
690‑020‑0047
Design Requirements for New Dams or to Increase Dam Height: Geosynthetics
690‑020‑0048
Exceptions to Standard Design Requirements
690‑020‑0055
Design Requirements for New Dams or to Increase Dam Height: Design Drawings
690‑020‑0060
Design Requirements for New Dams or to Increase Dam Height: Construction Specifications
690‑020‑0065
Plan Requirements for New Dams or to Increase Dam Height: Construction Administration
690‑020‑0068
Plan Requirements for New Dams or to Increase Dam Height: Operations and Maintenance Plan
690‑020‑0070
New Dams or to Increase Dam Height: Submittals and Notifications by the Engineer of Record
690‑020‑0080
New Dams, or to Increase Dam Height, Written Approval by State Engineer
690‑020‑0100
Hazard Rating of Dams
690‑020‑0120
Dam Breach Inundation Analysis
690‑020‑0140
Modification of Dams
690‑020‑0160
Removal
690‑020‑0180
Requirement of Owners to Provide Contact and Transfer of Title Information
690‑020‑0250
Maintenance of Dams
690‑020‑0260
Inspection of Dams
690‑020‑0310
Requirement to Address Maintenance Actions Need for High or Significant Hazard Dams
690‑020‑0340
Potentially Unsafe or Unsafe Conditions
690‑020‑0400
Emergency Action Plans (EAP)
690‑020‑0420
Immediate Action to Prevent Dam Failure
690‑020‑0460
Proposed Final Order, Request for Hearing, Contested Case Process
690‑020‑0600
Civil Penalty Assessment for Dam Safety
Last Updated

Jun. 8, 2021

Rule 690-020-0065’s source at or​.us