OAR 690-020-0070
New Dams or to Increase Dam Height: Submittals and Notifications by the Engineer of Record


(1)

The Engineer of Record must include an inundation analysis that complies with OAR 690-020-0120 (Dam Breach Inundation Analysis) prior to submitting the design report, plans and specifications and other documents, so that the Department can determine the Hazard Rating of the Dam.

(2)

All final designs, drawings and specifications submitted to the State Engineer for approval must be prepared and stamped by an Engineer. The first page of the drawings, the specifications, and the construction administration plan must be stamped by the Engineer of Record. All submitted materials must be addressed directly to the State Engineer and labeled as a Dam safety submission.

(3)

Final drawings shall be submitted on full size paper. The design reports and specifications must be submitted as packaged 8.5“ x 11” bound documents, with maps folded within.

(4)

For High Hazard Dams, the final Emergency Action Plan and any additional inundation analysis required for the EAP as described in OAR 690-020-0400 (Emergency Action Plans (EAP)) must be submitted by the Dam owner, or the Engineer of Record on behalf of the Dam owner, prior to commencing construction.

(5)

A schedule of construction shall be provided to the State Engineer prior to initiating construction of any Significant or High Hazard Dam.

(6)

The Engineer of Record shall notify the State Engineer to allow for Department inspection of the excavation prior to completion of the Cutoff Trench and all stripping of Foundation and Embankments. The required notice to the State Engineer is as follows:

(a)

48-hours for a Low Hazard Dam;

(b)

120-hours for a Significant Hazard Dam; and

(c)

240-hours or the time specified in the approval, whichever is longer, for High Hazard Dams.

(7)

Any changes made to the designed location, Height or width of the Dam, or to materials used in Dam construction shall be reported in writing immediately to the State Engineer.

(8)

Any slope instability observed during construction in the Embankment or adjacent to the Dam or into reservoir, shall immediately be reported to the State Engineer by phone.

(9)

The Engineer of Record must immediately notify the State Engineer if they are no longer the Engineer of Record. The notification shall be by phone and in writing.

(10)

The Engineer of Record must submit a project completion report upon completion of the Dam. A project completion report must include the following:

(a)

As-built Drawings. If possible, As-built Drawings shall be on the same sheet as the initial design drawings;

(b)

Sufficient information to document that the Dam has been built according to the drawings with changes to improve safety as documented in the As-built Drawings, or that critical safety functions are unknown;

(c)

A list of the dates the Engineer of Record was on site, the number and location of material tests, and observations of all changed conditions;

(d)

Material testing results (compaction, strength, permeability);

(e)

Observations and decisions made and communicated to the contractor or Dam owner;

(f)

Photographs of key stages of construction, including, but not limited to, photographs of the Cutoff Trench, borrow pit development, trenching and placement of the Conduit, the Spillway before and after placement of concrete; and

(g)

The signed professional stamp of the Engineer of Record.

Source: Rule 690-020-0070 — New Dams or to Increase Dam Height: Submittals and Notifications by the Engineer of Record, https://secure.­sos.­state.­or.­us/oard/view.­action?ruleNumber=690-020-0070.

690‑020‑0000
Purpose and Applicability
690‑020‑0022
Definitions
690‑020‑0024
General Department Authorities and Intergovernmental Coordination
690‑020‑0026
Fees
690‑020‑0028
Preliminary Plans and Specifications for Construction of New Dams or to Increase Dam Height
690‑020‑0035
Minimum Engineering Requirements for Final Design of New Dams or to Increase Dam Height
690‑020‑0036
Design Requirements for New Dams or to Increase Dam Height: Site Suitability and Geotechnical Evaluation
690‑020‑0037
Design Requirements for New Dams or to Increase Dam Height: Hydrology and Inflow Design Flood
690‑020‑0038
Design Requirements for New Dams or to Increase Dam Height: Embankment Dam Structures
690‑020‑0041
Design Requirements for New Dams or to Increase Dam Height: Concrete Dam Structures
690‑020‑0042
Minimum Design Requirements for New Dams or to Increase Dam Height: Spillways
690‑020‑0043
Design Requirements for New Dams or to Increase Dam Height: Penetrating Conduit(s) and Control of Flow through Conduits
690‑020‑0044
Design Requirements for New Dams or to Increase Dam Height: Instrumentation for Monitoring
690‑020‑0047
Design Requirements for New Dams or to Increase Dam Height: Geosynthetics
690‑020‑0048
Exceptions to Standard Design Requirements
690‑020‑0055
Design Requirements for New Dams or to Increase Dam Height: Design Drawings
690‑020‑0060
Design Requirements for New Dams or to Increase Dam Height: Construction Specifications
690‑020‑0065
Plan Requirements for New Dams or to Increase Dam Height: Construction Administration
690‑020‑0068
Plan Requirements for New Dams or to Increase Dam Height: Operations and Maintenance Plan
690‑020‑0070
New Dams or to Increase Dam Height: Submittals and Notifications by the Engineer of Record
690‑020‑0080
New Dams, or to Increase Dam Height, Written Approval by State Engineer
690‑020‑0100
Hazard Rating of Dams
690‑020‑0120
Dam Breach Inundation Analysis
690‑020‑0140
Modification of Dams
690‑020‑0160
Removal
690‑020‑0180
Requirement of Owners to Provide Contact and Transfer of Title Information
690‑020‑0250
Maintenance of Dams
690‑020‑0260
Inspection of Dams
690‑020‑0310
Requirement to Address Maintenance Actions Need for High or Significant Hazard Dams
690‑020‑0340
Potentially Unsafe or Unsafe Conditions
690‑020‑0400
Emergency Action Plans (EAP)
690‑020‑0420
Immediate Action to Prevent Dam Failure
690‑020‑0460
Proposed Final Order, Request for Hearing, Contested Case Process
690‑020‑0600
Civil Penalty Assessment for Dam Safety
Last Updated

Jun. 8, 2021

Rule 690-020-0070’s source at or​.us